81
5.2
Initial start-up (Initial Setup)
When the inverter is started up for the first time, initial setup starts automatically. This
procedure must only be carried out once during initial start-up. You can find information
on the operation of the graphics display in 6 “Operation”; page 83.
Requirements
n
Correctly connected DC supplies (AC connection is not required)
n
Sufficient solar irradiation
NOTE
n
You can restart initial start-up on the graphics display by pressing
at any time.
n
Thoroughly read the manual before starting initial start-up. Contact your grid op-
erator or the SolarMax Service Centre if you have any doubt regarding the settings
you must select.
Procedure
1. Switch on the DC disconnector Q1. The “Initial Setup” menu will be displayed on the
graphics display.
– Select the display language from the “Language” menu.
– Enter the current time.
– Enter today’s date. The inverter saves the date entered as the initial start-up date.
– Click
to confirm the entries.
2. Select the installation country in the “Country” menu.
CAUTION
Entering the country incorrectly may lead to problems regarding inverter operation and
to the withdrawal of the operating license by the respective grid operator.
– Press
to confirm your entry.
Steps 3 and 4: only for country settings “Germany” and “Italy”:
3. Select either “Low voltage” or “Medium voltage” in the “Grid connection” menu.
Summary of Contents for 10MT2
Page 59: ...118 en ...