82
en
Setting
Description
Mid voltage
The inverter is connected to the medium-voltage mains.
Low voltage
The inverter is connected to the low-voltage mains.
– Press
to confirm your entry. When selecting “Low voltage”, the “Plant type”
menu (for country setting “Germany”) or the “Standard” menu (for country setting
“Italy”) is displayed (step 4).
4. Determine the “Plant type” and/or the “Standard”.
“Plant type” menu.
Setting
Description
< 13.8kVA
The plant system rating is lower than 13.8kVA.
13.8–30kVA
The plant system rating is between 13.8kVA and 30kVA.
> 30kVA
The plant system rating is higher than 30kVA.
VDE 0126-1-1
Required setting if the inverter is commissioned within a PV plant connected to
the grid before 1 January 2012.
Note:
The setting “VDE 0126-1-1” is inadmissible for PV plants connected to the grid
after 31 December 2011.
– Press
to confirm your entry. With the “> 30kVA” setting, the “Monit. ext. in-
put” menu is displayed (step 5).
“Standard” menu:
Setting
Description
Guida Connessioni
Required setting if the inverter is commissioned within a PV plant connected to
the grid before 1 July 2012.
CEI 0-21
Required setting if the inverter is commissioned within a PV plant connected to
the grid after 30 June 2012.
– Press
to confirm your entry.
Steps 5 and 6: only for country setting “Germany”:
5. Configure the status signalling contact in the “Monit. ext. input” menu.
Setting
Description
On
The status signalling contact is configured for monitoring an external input. The
grid relays of the inverter are used as interconnection circuit breakers of the
central grid and plant protection. Description see section 4.6.5; page 77.
Inactive
The “Monitoring external input” function is switched off. The status signal-
ling contact can be used for remote retrieval of the inverter's operating status.
Description see section 4.6.4; page 77.
– Press
to confirm your entry.