104
en
Status message
Cause
Measure
Vac 10min too high (L1 L2 L3)
Vac 10min too high BP
(L1 L2 L3)
The maximum 10-minute
average value of the mains
voltage (Vac 10 min max.)
at the specified phase is too
high.
If this problem continues to
occur, contact the responsible
grid operator.
df/dt too high
The change in the mains
frequency per second has
exceeded the maximum
admissible value df/dt max.
Insulation fault DC
Insulation fault DC BP
The insulation resistance of
the PV generator against earth
is too low.
Check the PV generator.
Ierr too high
Ierr too high BP
The DC leakage current has
exceeded the admissible
absolute limit value lerr max.
Ierr step too high
Ierr step too high BP
The DC leakage current has
exceeded the admissible step
value.
L and N interchanged
A phase and the neutral
conductor are incorrectly con-
nected (interchanged).
Connect the AC supplies
correctly.
Error DC polarity
One or more DC connections
are connected incorrectly
(incorrect polarity).
Connect the DC supplies
correctly.
Error ext. input 1
The external G/P protection
has disconnected the inverter
from the grid.
If this problem continues to
occur, contact the responsible
grid operator.
10.2.4 Error
Status message
Cause
Measure
Device error (+ error code)
An internal error has occurred
in the inverter.
Check the two-digit error code
displayed and contact the
SolarMax Service Centre.
Summary of Contents for 10MT2