23
en
Example of a station with three TS-SV inverters:
D
d
d
d
1
2
7
6
5
1
1
3
4
Legend:
D
Clearance as set by country-specific regulations
d
1 metre
1
SolarMax TS-SV inverter
2
MCU
5
AC distribution
3
DC fuse box
6
Medium voltage transformer
4
Own power supply transformer
7
Medium voltage switchgear
4.3.1 Heating
The inverters are tested to operate at temperatures to -20 °C. Remember to check the
minimum operating temperatures of the other components and, if necessary, to install a
heating unit.
4.3.2 Excavating the construction site
The construction site must be excavated following the instructions of the station outfitter.
Stations fitted with a basement ventilation system must be effectively protected against
the intrusion of rain, snow and water through the lateral cooling shafts. There must be
drainage channels and pipes in place and the subsurface soil must be permeable.