2–12
Installing the SBC
Figure 2–11 Installing the Primary Breakout Module
2.7 Setting Up and Installing the Secondary Breakout Module
You have the option of installing a secondary breakout module that provides key-
board/mouse and parallel ports at the rear of your VME chassis.
Note
The secondary breakout module requires a minimum of 55 mm (2.13 in)
clearance behind the primary breakout module. This distance does not
allow for clearance for additional P2 connections. You must add addi-
tional clearance if you use additional connections.
To set up and install the secondary breakout module:
1.
Set the secondary breakout module jumpers.
To use the keyboard/mouse port on the secondary breakout module, you
must set the module’s jumpers as shown in Figure 2–12.
ML013264