The wall is composed of 2 x 2 plasterboard boards,12,5 mm thick, installed on a steel
frame construction. The interior of the wall is filled with mineral wool (≥ 100 kg/m³).
The minimum thickness of the wall is 100 mm.
Installation material is mineral wool (≥ 140 kg/m³) and fire protection coating.
625
625
> 440
625
625
> 440
1
2
3
1
6
5
7
INSTALLATIE
IN MASSIEVE WAND
(FIRE BATT/WEICHSCHOTT)
INSTALLATIE
1. Create an opening in the wall (Ø d + 200 mm) x (Ø d + 200 mm) and build the subframe
according to the drawing, see
. Bend the fixing bracket
(1)
90°.
2. Place the damper in the opening up to the wall limit mark
(7)
on the damper.
Damper blade must be closed during installation!
3. Close the space between casing and wall with two layers of mineral wool (5) (density 140 kg/m³
or more, 50 mm thick, coated on one side). Seal the connections of mineral wool with
intumescent fire resistant sealant (6). Mineral wool and damper casing must be coated with
2 mm thick fire protection coating. Damper casing should be coated up to profile protrusions.
*Multiple fire dampers can be installed next to each other or ceiling/wall with the
minimal distance of 30 mm between them. See
.
Test the operation of the damper blade!
>
>