De wThe wall is composed of 2 x 2 plasterboard boards, 12.5 mm thick, installed on a steel
frame construction. The interior of the wall is filled with mineral wool (≥ 100 kg/m³). The
minimum thickness of the wall is 100 mm.
Wall opening dimensions
Damper Ø d [mm]
Applique frame Ø D [mm]
Wall opening [mm]
100
Ø d + 105 mm
Ø d + 115 mm
125-180
Ø d + 95 mm
Ø d + 105 mm
200-315
Ø d + 80 mm
Ø d + 90 mm
1
2
FLEXIBLE WALL
INSTALLATION
APPLIQUE INSTALLATION FRAME
INSTALLATION
Create an opening according to the table below and build the subframe according to the
drawing, see
Damper blade must be closed during installation!
1. Place the fire damper in the opening.
2. Fasten the fire damper with screws (8 pcs, 4.8 x 60 mm).
Test the operation of the damper blade!
>
>