Remove the BS from its packaging and stand it upright. Check for visual damage.
All other items are contained in a box in one corner of the packaging. Remove them and
check whether any items are missing.
Note:
retain packaging for future storage or transportation.
Packing list
The following table lists each item and the numbers of these included. If anything is damaged
or missing, contact Soluna Australia or your distributor.
Item
Name
Qty
(pcs)
Remark
1
Soluna 10K PACK HV
1
2
Protective earthing conductor
(PE wire)
1
3
Inner-hexagon wrench (3.0)
1
4
Inner-hexagon wrench (4.0)
1
5
Inner-hexagon screws (M4)
4
6
Inner-hexagon screws (M6
)
2
7
Phillips screws
(
M6
)
10
8
Expansion screws
8
9
CAN communication wire
1
Installation materials
Installers should prepare the following installation materials.
1)
Battery connection / charging cables
2)
Network connection cables
Installation location
Ensure that the installation location meets the following requirements.
1)
The building is designed to withstand earthquakes.
2)
The BS location is internal and out of direct sunlight.
3)
The floor is flat and level.
4)
There are no flammable or explosive materials nearby.
5)
The ambient temperature is between 15° and 30° Celsius.
6)
The temperature and humidity remain at a constant level.
7)
There is minimal dust and/or dirt in the area.
8)
There are no corrosive gases present, including ammonia and acid vapour.
If the ambient temperature is outside the operating range, the BS will stop operating to
protect itself. The optimal operating temperature range for the BS is 15° to 30° Celsius.
Frequent exposure to harsh temperatures may adversely affect the performance and
longevity of the BS.