Further Installation Options:
It is not allowed to install the laminates in a roof-overhanging situation
.
To assure an ideal operation of the PV-generator you have to mind a sufficient
ventilation of the module.
During operation of the PV-plant it could be that the given technical values of tension
and current are in real higher than calculated before under STC. In order to prevent a
possible disproportion between theoretical and real values it is recommends to add a
security margin of 1,25 on all technical values including cable cross section, inverter
power
etc.
It has to be taken into consideration that the load of the PV-plant into the grid is
balanced on all three phases of the public power grid. All technical standards for grid-
feeding inverters have to be respected. In every case during development the
technical data-sheet of the inverter has to be taken into account.
All inverters have to respect the national and local grid-feeding standards including
EMC regulations.
It is requested to install on DC side a switch, which interrupts both poles of a string at
the same time. The switch has to make sure the galvanic separation
.