12
5. Connecting the TM-25R
5.1. Equipment location
The equipment shall be placed as close as possible to the tower support
where the grounding is located, and it will be connected to the instrument
E
terminal.
5.2. Auxiliary rods set up
Auxiliary rods will be set up in the ground, making a straight line with the
tower (point zero of measurements), perpendicular to the power
transmission line. Initially, the auxiliary current rod must be at a 100 m
distance and the probe (potential rod) at a 65 m distance. In order to
establish a connection with the farthest rod, a black cable must be used
together with the shielded cable (black) that must be connected to the
equipment, to the
H
connector. The central rod (probe) will be connected
to the equipment
S
terminal.
Earth Resistance
f= 25kHz
01/01/2014 17:21
E
S
H