Sectional Monopole Tower Foundation & Installation Manual, Revision A
13
Positioning the Foundation bolts (SMarT Foundation)
The SMarT Foundation includes a template as part of the foundation kit therefore the construction of a template is not required. Refer to the
SMarT Foundation instructions located in Appendix C of this manual.
Electrical Conduit
Electrical conduit may be cast into the foundation such that the conduit continues below grade to electrical panel. Alternately
wire may be routed between tower base plate and foundation. Refer to local building codes
bEFORE
pouring concrete.
Building codes typically require direct burial cables be buried to a minimum depth of 24 in (61 cm) while cables in conduit may be buried at a
depth of 18 in (46 cm). Additionally, most codes prohibit embedding cables directly in concrete. Refer to local codes for conduit size and mini-
mum depth requirements.
Tower Grounding
Refer to the Skystream Owner’s Manual for complete directions on grounding the tower. It is vital the tower be properly grounded to minimize risk
of electrical shock.
Completing the Foundation
Refer to the foundation technical drawings contained in the appendices of this manual for complete notes including; foundation dimensions, con-
struction notes and grading and concrete requirements. Regardless of the foundation 28 days are required for the concrete to cure to a minimum
compressive strength of 2500 PSI (17230 kPa).