18  

Sectional Monopole Tower Foundation & Installation Manual, Revision A

•  Install the second U-Bolt clip as near the thimble as possible. As with the previous U-Bolt clip, tighten the nuts evenly, alternating from one nut to the 
   other until reaching 30 lb-ft (41 N-m) of torque.

•  Install the third U-Bolt clip midway between the other clips and tighten the nuts to 30 lb-ft (41 N-m) of torque.

•  Apply a load to the cable equal or greater than the maximum anticipated load (DO NOT USE THE TOWER AND TURBINE AS THE LOAD) and retighten 
   the nuts to 30 lb-ft (41 N-m) of torque. This step is very important as the cable may stretch and shrink in diameter when a load is applied effectively loos
   ing the U-Bolt clip nuts. Note the maximum load the cable will experience is approximately 2400 lb (1100 kg).

Raising the Tower - (continued)

•  Connect the second wire rope cable to the base of the gin pole and to the “lifting” vehicle using the shackles provided.

•  Start to “raise’ the tower by slowly driving the “lifting” vehicle away from the tower to take the slack out of the cable – keep the vehicle “in line” with the    
   tower – avoid loading the tower in a lateral direction.

•  The vehicle should stop pulling as the end of the gin pole approaches 3-4 ft (1-1.3 m) above ground level. At this point two full size adults can complete 
   raising the tower by pushing down on the end of the gin pole or by pushing down on the cable.

•  Observe that the anchor bolt closest to the hinge pivot axis clears the slot in the tower base. This is normally not an issue unless the anchor bolt projec-
   tion from the foundation exceeds 7.5 in (19 cm).

•  As the tower nears the fully vertical position it will be necessary to “lift” the gin pole to slow the tower as it assumes the fully vertical position. Two people 
   are required for this operation.

•  When the tower is completely vertical install the remaining nuts and washers to secure the tower to the foundation.

If the tower was raised without the turbine, refer to the section on lowering the tower. If the tower was raised with the turbine proceed to the section on 
Leveling the Tower.

CORRECT

6 in (15 cm)

WRONG

WRONG

Summary of Contents for SkyStream 3.7

Page 1: ...OWER do not manually update scale 1 8 size A CAD file dwg sheet 1 of 1 rev NC DATE APPROVALS DRAWN R D PROD EGR MFG QUAL MATERIAL FINISH DO NOT SCALE DRAWING DWG CAD generated drawing X 1 30 decimals...

Page 2: ...Positioning the Foundations Bolts Pier Mat Foundations _ __11 12 Positioning the Foundations Bolts SMarT Foundation _____ 13 Electrical Conduit_____________________________________ 13 Completing the...

Page 3: ...ction and tower installation 4 Install foundation and tower in accordance with National Electric Code and all local building and zoning codes and requirements 5 Obtain building and construction permit...

Page 4: ...d to construct a foundation for Southwest Windpower s Monopole Towers For the Pier and Mat foundations the information in the manual is sufficient for individuals knowledgeable in working with concret...

Page 5: ...etting into before starting Owners should also be aware that many localities require installation by certified installers or by licensed contrac tors to qualify for clean energy monetary rebates If yo...

Page 6: ...and available open space may require Skystream be installed in a less than optimum location At a minimum try to observe the following general rule for siting the turbine TIP Your dealer can help you...

Page 7: ...the tower over 60 ft 20 m may be required on the other side of the foundation for the vehicle pulling cable and gin pole Slightly less space is required to raise the 33 5 ft 10 2 m tower Refer to the...

Page 8: ...ds The dimensions and construction details for each of the foundations will change based on the anticipated wind speed Refer to the accompanying tables to determine your Wind Speed Zone and the locati...

Page 9: ...andy Gravel and or Gravel 4 Sand Silty Sand Clayey Sand Silty Gravel and Clayey Gravel SW SP SM SC GM and GC 5 Clay Sandy Clay Silty Clay Clayey Silt Silt and Sandy Silt CL ML MH and CH Tower Height F...

Page 10: ...foundation depth In summary consult with a number of contractors and with local building inspectors to achieve the best foundation value Foundation Bolts and Templates Two foundation bolt kits are av...

Page 11: ...the tower to the foundation Using the paper template supplied with the foundation bolt kit as a guide construct a wooden template to position the foundation J bolts 1 2 in 13 mm or 3 4 in 19 mm plywo...

Page 12: ...TEMPLATE IMPORTANT Do not exceed 7 0 0 38 inches 18 0 cm 10 mm dimension or bolts may interfere with hinge plate TOP OF PIER TOP OF ANCHOR BOLT TOP OF WASHER THESE DIMENSIONS MUST BE OBSERVED 7 00 17...

Page 13: ...require direct burial cables be buried to a minimum depth of 24 in 61 cm while cables in conduit may be buried at a depth of 18 in 46 cm Additionally most codes prohibit embedding cables directly in...

Page 14: ...o secure the hinge plate and thread three nuts and washers washer below nut to secure the hinge plate in place Fully tighten the hinge plate to the foundation using the Turn of the Nut method describe...

Page 15: ...be bolted to the hinge plate and foundation and gin pole Perform the following steps to join the tower segments using the gin pole to assist with the process Refer to accompanying figure TOP OF PIER T...

Page 16: ...ole approximately 10 to 20 degrees above horizontal and insert chain links into the slotted plates positioned on either side of the gin pole s central support tube The gin pole should maintain its pos...

Page 17: ...the length of this cable when switching between the 33 5 ft 10 2 m and 45 ft 13 7 m towers or because of variations in the location of the lifting tab Refer to the accompanying Adjusting Cable Length...

Page 18: ...ower by slowly driving the lifting vehicle away from the tower to take the slack out of the cable keep the vehicle in line with the tower avoid loading the tower in a lateral direction The vehicle sho...

Page 19: ...tion section of this manual Observe the recommended bolt tightening procedure Connect the gin pole to the lifting tab at the mid section of the tower using the wire rope cable and shackles provide wit...

Page 20: ...ystream on calm days If the wind turbine seems to favor a single position with no wind the tower may require fine tuning even if it appears level using the bubble leveling technique To fine tune the t...

Reviews: