 Installation Manual, Rev A

    

15

20.  Using a compass, find magnetic North.  Adjust the compass by the 

magnetic declination value (while the needle stays at magnetic North, 
rotate the compass counter-clockwise for easterly (+) declinations, 
and clockwise for westerly (-) declinations.  See Figure 11.     

21.  Rotate the sun tracker assembly until the solar panels are facing true 

South (180º from true North).  

Figure 12

22.  Install two spacers, 3/8”-16 x 1-1/2” bolts, and hex flange lock nuts 

(from the hard stop hardware package) on the tower gear in the loca-
tions shown.  See Figure 12.

23.  Install the chain around the tower gear and motor sprocket by install-

ing the master link and attaching the clip.  See Figure 10.

24.  Ensure the assembly is still aligned with true South, and tighten chain 

tension.  Check that chain play is similar on both sides of the sprocket.  
Once desired tension is reached, tighten the four motor/gearbox bolts 
located underneath the frame assembly to lock in place.  See Figure 10.

25.  Install the sun tracker cover assembly to the tower, above the  

sun tracker assembly.  Tighten using the pipe clamp, and install  
the two screws. 

19.  Prior to installing the chain, the solar panels must be facing true South 

(if in the Northern hemisphere) prior to power-up.  True South dif-
fers from magnetic South.  In order to find true South, the magnetic 
declination for the installation location must be found.  The magnetic 
declination value represents the error between magnetic North and 
True North for a specific location.  This value can be represented as an 
easterly (positive (+)) declination, or a westerly (negative (-)) declina-
tion.  There are two ways to find the magnetic declination:

1.  go to: http://www.ngdc.noaa.gov/geomagmodels/declination.

jsp, enter the zip code for the installation location and click “get 
location.”  Then click “Compute declination” and find the declina-
tion in the lower box.  

2.  looking at the following chart, use the blue and red lines to find 

the approximate magnetic declination for the installation location.  
These values vary slightly from year to year, but this chart is suf-
ficient for an approximate value.

MAGNETIC DECLINATION FOR THE U.S. - 2010

Contour Interval: 1 Degree (Positive declinations in blue, negative in red)

Figure 12

Figure 11

Summary of Contents for Skystream Hybrid 6

Page 1: ...ition The installer is solely responsible for complying with all applicable building and electrical codes To help prevent stainless steel hardware from seizing together 1 apply anti seize lubricant to...

Page 2: ......

Page 3: ..._______________________________________ 11 cross arm structure assembly and installation_______________________ 13 motor gearbox installation_____________________________________________ 14 alignment...

Page 4: ...ackages One pallet contains the shell assemblies and three boxes of hardware The boxes of hard ware are packaged inside of the shell assemblies The second package will be a 6 X 6 x 11 box containing f...

Page 5: ...Hybrid 6tm system 7 Maintain tightness of fasteners according to torque requirements see Maintenance and Inspections Professional installation Southwest Windpower strongly recommends Skystream Hybrid...

Page 6: ...n the shortest practical path to a suitable electrical connection point In most cases this connection point will be the main service panel In any event it should be as close as possible to the point w...

Page 7: ...ower lifting mecha nisms are suitable for raising the tower with the Skystream 3 7tm and the solar tracker installed If the solar tracker is installed on a tower in the upright position appropriate li...

Page 8: ...of the base flange For installation on a 45 19 tower with 4 feet of clearance between the tower base flange and the lowest point of the PV array make a mark 106 inches from the bottom of the base fla...

Page 9: ...is located on the North side of the tower drill a hole for your cord grip or strain relief fitting The diameter of the hole will depend upon the size of your specified electrical cable and your ground...

Page 10: ...unting hardware for each tapered ring See Figure 2 After tightening the four tapered rings should fit flush to each other without gaps 3 Install the remaining four tapered rings to the top side of the...

Page 11: ...e outside of the assembly for easy removal See Figure 4 7 Loosely re insert a 5 16 18 X screw no washers into the center hole on each side of the cross arm side support shell assembly This will help g...

Page 12: ...e tower after tightening If too much play still exists re adjust all rollers the same amount Tighten the jamb nuts once all rollers are adjusted Confirm the shell assemblies roll freely around the tow...

Page 13: ...for Motech 235W solar panels Temporarily leave the bolts loose 15 Install the two solar panel inverter support rails onto the mounting brackets closest to the sun tracker assembly Ensure the rails are...

Page 14: ...perimeter edge lip facing downwards should overlap the top edge of the solar tracker assembly approximately 1 2 inch Alignment and Chain Installation 19 Prior to installing the chain the solar panels...

Page 15: ...rd stop hardware package on the tower gear in the loca tions shown See Figure 12 23 Install the chain around the tower gear and motor sprocket by install ing the master link and attaching the clip See...

Page 16: ...diagram as always however your local AHJ may modify these or may impose additional requirements 1 Using the mounting brackets supplied with the six micro inverters mount them onto the solar panel inve...

Page 17: ...ve compatible Tyco Solarlok connectors The PV module connectors simply plug into the Enphase micro inverter input connectors Install the two WEEBL ground lugs to the rails in the locations shown and r...

Page 18: ...es where appropriate 3 Run a ground cable and an AC cable through the strain relief or fitting to the base of the pole Make connections in the base of the pole A normal new installation will have a su...

Page 19: ...in the OFF position and con nect the motor cable to the connector coming from the control enclo sure Turn the switch to the ON position CAUTION MOTION The controller super capacitors will begin to ch...

Page 20: ...20 Skystream Hybrid 6tm Installation Manual Rev A...

Page 21: ...dpower Inc 1801 West Route 66 Flagstaff Arizona 86001 Phone 1 928 779 9463 Fax 1 928 779 1485 www windenergy com appendix a electrical diagrams January 2012 Southwest Windpower Inc Inc All Rights Rese...

Page 22: ...Installation Manual Rev A Skystream Hybrid 6tm Installation Manual Appendix A Electrical Diagrams 1 Grid Connection Option A 120 240 V 60 Hz Split Phase Sub panel at Tower Base________________________...

Page 23: ...Skystream Hybrid 6tm Installation Manual Rev A 23 Fig 1 Grid Connection Option A 120 240 V 60 Hz Split Phase Sub panel at Tower Base...

Reviews: