 Skystream hybrid 6

TM

 Installation Manual, Rev A

    

19

4.  Make the connections at the system disconnect, optional meter, and 

at the main panel connection point (circuit to be protected by a 40A 
double pole  breaker).

5.  Remove Stop Screw if installed.

6.  Re-install the enclosure cover and cover bolts that were removed in 

Step 18.

7.  Ensure the tracker controller switch is in the “OFF” position, and con-

nect the motor cable to the connector coming from the control enclo-
sure.  Turn the switch to the “ON” position.  

 

CAuTION – mOTION:  The controller super-capacitors will begin 

to charge up once the solar panels are connected to the control-

ler.  After the controller switch is turned “ON” and a gPS signal 

is acquired, the controller calculates the sun position, and track-

ing will begin.  Tracking motion occurs on the 10-minute mark.  

(The tracker will return to South at low power conditions.  (AC 

does not have to be connected for tracker operation).

 

Summary of Contents for Skystream Hybrid 6

Page 1: ...ition The installer is solely responsible for complying with all applicable building and electrical codes To help prevent stainless steel hardware from seizing together 1 apply anti seize lubricant to...

Page 2: ......

Page 3: ..._______________________________________ 11 cross arm structure assembly and installation_______________________ 13 motor gearbox installation_____________________________________________ 14 alignment...

Page 4: ...ackages One pallet contains the shell assemblies and three boxes of hardware The boxes of hard ware are packaged inside of the shell assemblies The second package will be a 6 X 6 x 11 box containing f...

Page 5: ...Hybrid 6tm system 7 Maintain tightness of fasteners according to torque requirements see Maintenance and Inspections Professional installation Southwest Windpower strongly recommends Skystream Hybrid...

Page 6: ...n the shortest practical path to a suitable electrical connection point In most cases this connection point will be the main service panel In any event it should be as close as possible to the point w...

Page 7: ...ower lifting mecha nisms are suitable for raising the tower with the Skystream 3 7tm and the solar tracker installed If the solar tracker is installed on a tower in the upright position appropriate li...

Page 8: ...of the base flange For installation on a 45 19 tower with 4 feet of clearance between the tower base flange and the lowest point of the PV array make a mark 106 inches from the bottom of the base fla...

Page 9: ...is located on the North side of the tower drill a hole for your cord grip or strain relief fitting The diameter of the hole will depend upon the size of your specified electrical cable and your ground...

Page 10: ...unting hardware for each tapered ring See Figure 2 After tightening the four tapered rings should fit flush to each other without gaps 3 Install the remaining four tapered rings to the top side of the...

Page 11: ...e outside of the assembly for easy removal See Figure 4 7 Loosely re insert a 5 16 18 X screw no washers into the center hole on each side of the cross arm side support shell assembly This will help g...

Page 12: ...e tower after tightening If too much play still exists re adjust all rollers the same amount Tighten the jamb nuts once all rollers are adjusted Confirm the shell assemblies roll freely around the tow...

Page 13: ...for Motech 235W solar panels Temporarily leave the bolts loose 15 Install the two solar panel inverter support rails onto the mounting brackets closest to the sun tracker assembly Ensure the rails are...

Page 14: ...perimeter edge lip facing downwards should overlap the top edge of the solar tracker assembly approximately 1 2 inch Alignment and Chain Installation 19 Prior to installing the chain the solar panels...

Page 15: ...rd stop hardware package on the tower gear in the loca tions shown See Figure 12 23 Install the chain around the tower gear and motor sprocket by install ing the master link and attaching the clip See...

Page 16: ...diagram as always however your local AHJ may modify these or may impose additional requirements 1 Using the mounting brackets supplied with the six micro inverters mount them onto the solar panel inve...

Page 17: ...ve compatible Tyco Solarlok connectors The PV module connectors simply plug into the Enphase micro inverter input connectors Install the two WEEBL ground lugs to the rails in the locations shown and r...

Page 18: ...es where appropriate 3 Run a ground cable and an AC cable through the strain relief or fitting to the base of the pole Make connections in the base of the pole A normal new installation will have a su...

Page 19: ...in the OFF position and con nect the motor cable to the connector coming from the control enclo sure Turn the switch to the ON position CAUTION MOTION The controller super capacitors will begin to ch...

Page 20: ...20 Skystream Hybrid 6tm Installation Manual Rev A...

Page 21: ...dpower Inc 1801 West Route 66 Flagstaff Arizona 86001 Phone 1 928 779 9463 Fax 1 928 779 1485 www windenergy com appendix a electrical diagrams January 2012 Southwest Windpower Inc Inc All Rights Rese...

Page 22: ...Installation Manual Rev A Skystream Hybrid 6tm Installation Manual Appendix A Electrical Diagrams 1 Grid Connection Option A 120 240 V 60 Hz Split Phase Sub panel at Tower Base________________________...

Page 23: ...Skystream Hybrid 6tm Installation Manual Rev A 23 Fig 1 Grid Connection Option A 120 240 V 60 Hz Split Phase Sub panel at Tower Base...

Reviews: