IM-P402-62  AB Issue 5

8

To commission the transmitter proceed as follows:-

1. Ensure the transmitter is set up for the correct functions and mains supply voltage.

2. Alter the water level in the tank or boiler to

the required low level, or zero point. This is

the

point at which you require the 4 mA, (or 0 mA) to be transmitted.

3. Adjust the zero adjust potentiometer (bottom) until the > 0% LED just lights.

4. Alter the water level to the required high level. This is the level at which the 20 mA signal is

to be transmitted. (Note: that these output signals will be reversed if 'reverse action'
as been selected on switch 3).

5. Adjust the span adjust potentiometer (top) until the > 100% LED just lights.

6. As an aid to commissioning, an ammeter may be connected across the test output pins (5

and 6), to indicate transmitted current.

6. Commissioning

7. Maintenance

8. Fault finding

No special servicing or maintenance of the transmitter is necessary.  Boiler water level controls
and level alarms, however, do require testing and inspection. General guidance is given in Health
and Safety Executive Guidance Note PM5.
For specific instructions for the Spirax Sarco system please see separate literature.

Available spares

Spare fuses

Stock No. 4033380

Set of 3

Most faults which occur on commissioning are due to incorrect wiring or setting up.
In the case of problems the following checklist may be helpful:-

Mains on LED not lit:

-

No live supply

-

Neutral not connected

-

Transmitter internal fuse blown.

Transmitter internal fuse blown:

-

Check the mains supply voltage is lower than 264 V, and that the ambient temperature inside
the control panel is less than 55°C (131°F). If either of these limits has been exceeded, it
is possible that the transformer internal thermal fuse has blown, and that the transformer
will need to be replaced.

-

Ensure that the probe supply voltage is between 24 Vdc and 35 Vdc between terminals 10 and
12 of the transmitter, or terminals 1 and earth of the probe.

-

The probe output voltage should be 1 Vdc to 6 Vdc between terminals 11 and 12 of the
transmitter, or terminals 2 and earth of the probe, depending on the level.

-

The voltage increases with the level, even when inverse output has been selected.

Summary of Contents for LT2010

Page 1: ... Maintenance Instructions IM P402 62 AB Issue 5 4025351 5 1 General safety information 2 General product information 3 Installation 4 Settingupthetransmitter 5 Wiring diagrams 6 Commissioning 7 Maintenance 8 Fault finding LT2010 100 0 Printed in the UK Copyright 2003 ...

Page 2: ...e injury or fatality to personnel Warning Isolate the mains supply before unplugging the transmitter since hazardous voltages will be exposed on the transmitter base This product complies with the requirements of Electromagnetic Compatibility Directive 89 336 EEC by meeting the standards of BS EN 50081 1 Emissions and BS EN 61000 6 2 Immunity The following conditions should be avoided as they may ...

Page 3: ...e very different turbulence conditions found in tanks and high output boilers The LT2010 is set up before installation to suit the mains supply voltage and to provide the required functions using internal switches See Setting up the transmitter Section 4 Calibration can be altered without removing or dismantling the unit using the zero point and full scale span potentiometers on the front panel Ma...

Page 4: ...screwed directly to a chassis plate Caution Allow 15 mm spacing between multiple units for air circulation The transmitter is for installation Category II Overvoltage category and must be installed in accordance with IEC 60364 or equivalent The transmitter and all connected circuits must have a common isolation system which meets the relevant requirements of IEC 60947 1 and IEC 60947 3 or equivale...

Page 5: ...e with a temperature transmitter for example set switch 1 and 2 to ON 4 5 Inverse output Switch 3 The transmitter is supplied set so that a rising level at the probe will give a rising output from the transmitter If a falling transmitter output is required with a rising input as when using a differential pressure transmitter for level monitoring set Switch 3 to OFF 4 6 Wave filter Switch 8 This fe...

Page 6: ... from electric shock under a single fault condition This product has double insulation and therefore does not require a protective earth A functional earth is used in order for the product to operate In this application the earth tank boiler shell is used as the common of the probe preamplifier It also provides a sink drain for any electrical interference Ensure that the screen is connected to the...

Page 7: ...itter powered from the LT2010 Additional unit Multiple transmitters Several transmitters can be connected to a single probe if required Connect wiring as shown in the diagram Ensure resistance from probe body to pipework boiler shell is less than 1 W Links on preamplifier provide sensitivity selection see preamplifier IMI The earth pin is internally connected to the PA20 body and earthed by the LP...

Page 8: ...ing and inspection General guidance is given in Health and Safety Executive Guidance Note PM5 For specific instructions for the Spirax Sarco system please see separate literature Available spares Spare fuses Stock No 4033380 Set of 3 Most faults which occur on commissioning are due to incorrect wiring or setting up In the case of problems the following checklist may be helpful Mains on LED not lit...

Reviews: