background image

17

GAS PIPING

 To avoid equipment damage or possible personal injury, do not connect gas piping to

this unit until a supply line pressure/leak test has been completed. Connecting the unit before
completing the pressure/leak test may damage the unit gas valve and result in a fire hazard.

Do not rely on a shut off valve to isolate the unit while conducting gas pressure/leak tests. These valves
may not be completely shut off, exposing the unit gas valve to excessive pressure and damage.

PIPE SIZING

To provide adequate gas pressure at the gas duct
furnace, size the gas piping as follows:
1.

Find the cu ft/hr by using the following formula:

                        Input

Cu ft/hr =

                         Btu
2.

Refer to Table 5. Match “Pipe Run in Feet” with
appropriate “Gas Input - Cu Ft/Hr” figure. This
figure can then be matched to the pipe size at the
end of the column.

Example: It is determined that a 67 foot (20.4m) run of gas
pipe is required to connect a 200 MBTU gas duct furnace
to a 1,000 Btu/cu. ft (0.29 kW) natural gas supply.

200,000 Btu/hr

                              = 200 Cu ft/hr
 1,000 Btu/cu ft

Using Table 5, a 1 inch nominal diameter pipe is needed.

NOTICE: See General Safety Information section
for english/SI (metric) unit conversion factors.

Nominal

Iron

Pipe Size

Internal

Dia.

Maximum Capacity of Pipe in Cubic Feet of Gas per Hour for Gas Pressures of 0.5 psig (3.5 kPa) or Less,

and a Pressure Drop of 0.5 Inch Water Column (124.4 Pa)

(Based on a 0.60 Specific Gravity Gas)

Length of Pipe, ft. (Meters)

GAS PIPE SIZE

in.

in.

10

20

30

40

50

60

70

80

90

100

125

150

175

200

(mm)

(3.0)

(6.1)

(9.1)

(12.2)

(15.2) (18.3)

(21.3)

(24.4)

(27.4)

(30.5)

(38.1)

(45.7)

(53.3)

(61.0)

 1/2

0.622

175

120

97

82

73

66

61

57

53

50

44

40

37

35

(16)

(4.96)

(3.40)

(2.75)

(2.32)

(2.07) (1.87)

(1.73)

(1.61)

(1.50)

(1.42)

(1.25)

(1.13)

(1.05)

(0.99)

 3/4

0.824

360

250

200

170

151

138

125

118

110

103

93

84

77

72

(21)

(10.2)

(7.08)

(5.66)

(4.81)

(4.28) (3.91)

(3.54)

(3.34)

(3.11)

(2.92)

(2.63)

(2.38)

(2.18)

(2.04)

1

1.049

680

465

375

320

285

260

240

220

205

195

175

160

145

135

(27)

(19.3)

(13.2)

(10.6)

(9.06)

(8.07) (7.36)

(6.80)

(6.23)

(5.80)

(5.52)

(4.96)

(4.53)

(4.11)

(3.82)

1 1/4

1.380

1400

950

770

660

580

530

490

460

430

400

360

325

300

280

(35)

(39.6)

(26.9)

(21.8)

(18.7)

(16.4) (15.0)

(13.9)

(13.0)

(12.2)

(11.3)

(10.2)

(9.20)

(8.50)

(7.93)

1 1/2

1.610

2100

1460

1180

990

900

810

750

690

650

620

550

500

460

430

(41)

(59.5)

(41.3)

(33.4)

(28.0)

(25.5) (22.9)

(21.2)

(19.5)

(18.4)

(17.6)

(15.6)

(14.2)

(13.0)

(12.2)

2

2.067

3950

2750

2200

1900

1680

1520

1400

1300

1220

1150

1020

950

850

800

(53)

(112)

(77.9)

(62.3)

(53.8)

(47.6) (43.0)

(39.6)

(36.8)

(34.5)

(32.6)

(28.9)

(26.9)

(24.1)

(22.7)

2 1/2

2.469

6300

4350

3520

3000

2650

2400

2250

2050

1950

1850

1650

1500

1370

1280

(63)

(178)

(123)

(99.7)

(85.0)

(75.0) (68.0)

(63.7)

(58.0)

(55.2)

(52.4)

(46.7)

(42.5)

(38.8)

(36.2)

3

3.068

11000

7700

6250

5300

4750

4300

3900

3700

3450

3250

2950

2650

2450

2280

(78)

(311)

(218)

(177)

(150)

(135)

(122)

(110)

(105)

(97.7)

(92.0)

(83.5)

(75.0)

(69.4)

(64.6)

4

4.026

23000

15800

12800

10900

9700

8800

8100

7500

7200

6700

6000

5500

5000

4600

(102)

(651)

(447)

(362)

(309)

(275)

(249)

(229)

(212)

(204)

(190)

(170)

(156)

(142)

(130)

1.  Determine the required Cu. Ft. / Hr. by dividing the rated heater input by 1000.    2.  FOR NATURAL GAS:  Select the pipe size directly
from the table.    3.  FOR PROPANE GAS:  Multiply the Cu. Ft. / Hr. value by 0.633; then use the table.    4.  Refer to the metric conversion
factors listed in General Safety section for SI unit measurements/conversions.

Table 5

NOTICE: If more than one gas duct furnace is to be
served by the same piping arrangement, the total cu
ft/hr input and length of pipe must be considered.

NOTICE:  If the gas duct furnace is to be fired with
LP gas, see below and consult the local LP gas
dealer for pipe size information.

NOTICE: HEATER INSTALLATION FOR USE WITH
PROPANE (BOTTLED) GAS MUST BE MADE BY A
QUALIFIED L.P. GAS DEALER OR INSTALLER.  HE
WILL INSURE THAT PROPER JOINT COMPOUNDS
ARE USED FOR MAKING PIPE CONNECTIONS; THAT
AIR IS PURGED FROM LINES; THAT A THOROUGH
TEST IS MADE FOR LEAKS BEFORE OPERATING
HEATER; AND THAT IT IS PROPERLY CONNECTED
TO PROPANE GAS SUPPLY SYSTEM.

Before any connection is made to an existing line
supplying other gas appliances, contact the local gas
company to make certain that the existing line is of
adequate size to handle the combined load.

Summary of Contents for NATURAL INDOOR GAS-FIRED DUCT FURNACE

Page 1: ...th defects or other reproductive harm INSTALLER S RESPONSIBILITY Installer Please Note This equipment has been test fired and inspected It has been shipped free from defects from our factory However s...

Page 2: ...to in this manual are the ones that were applicable at the time the design was certified In addition the duct furnace may be installed on the downstream side of a cooling unit without need of a bypas...

Page 3: ...k tested by a suitably qualified individual per instructions in this manual Also follow procedures listed on the Gas Equipment Start up sheet located in this manual Use only the fuel for which the hea...

Page 4: ...RH 1 2 1 2 221 664 603 645 816 203 RH 100 225 28 7 8 26 1 2 28 1 8 34 7 8 8 RH 3 4 1 2 OR 3 4 243 733 673 714 886 203 RH 110 250 31 5 8 29 1 4 30 7 8 37 5 8 8 RH 3 4 1 2 OR 3 4 252 803 743 784 956 203...

Page 5: ...5 8 18 1 4 19 7 8 4 26 5 8 1 2 1 2 197 524 464 505 102 676 89 175 23 3 8 21 22 5 8 4 29 3 8 1 2 1 2 216 594 533 575 102 746 98 200 26 1 8 23 3 4 25 3 8 5 32 1 8 1 2 1 2 232 664 603 645 127 816 105 225...

Page 6: ...ater SIZE kW kW kW cu m s Deg C kPa cu m s Deg C Pascals 100 100 50 80 929 80 0 12 2469 30 0 90 29 3 14 6 23 4 0 438 44 0 03 1 165 17 0 22 125 125 62 5 100 1157 80 0 13 3086 30 0 80 36 6 18 3 29 3 0 5...

Page 7: ...allow a minimum of 21 inches 533mm at the bottom of the unit to facilitate servicing the burners and pilot or six inches 152mm if the unit has a side access burner drawer Provision should also be made...

Page 8: ...of mechanical vibration AIR FLOW The installation is to be adjusted to obtain an air throughput within the range specified on the appliance rating plate INSTALLATION COMBUSTION INLET AIR VENTILATION I...

Page 9: ...EOFSAFELYSUPPORTINGITS WEIGHT UNDER NO CIRCUMSTANCES MUST THE GAS LINES VENTING SYSTEM OR THE ELECTRICAL CONDUIT BE USED TO SUPPORT THE HEATER OR ANY OTHER OBJECTS I E LADDER PERSON LEAN AGAINST THE H...

Page 10: ...where drafts may affect the operation of the control 2 Hot areas Areas where the sun s rays radiation or warm air currents may affect control operation 3 Dead areas Areas where air cannot circulate fr...

Page 11: ...mon flue the cross sectional area of the common flue must be equal to the largest vent connection plus 50 of the area of each additional vent connection 3 Provide as long a vertical run of flue at the...

Page 12: ...ired from the venter outlet before installing an elbow in the vent system An elbow should never be attached directly to the venter Use single wall pipe constructed of 26 gauge galvanized steel or mate...

Page 13: ...sfor Structure Termination Locations 4 feet below Door window or any gravity air inlet 4 feet horizontally 1 foot above Forced air inlet within 10 ft 3 feet above Adjoining building or parapet 6 feet...

Page 14: ...14 Figure 12A Figure 12B...

Page 15: ...15 Figure 13A Figure 13B...

Page 16: ...Cap At Lowest Point Of Vent System Typ D4072 To Horizontal Flue Vent Termination Reducer Increaser Where Applicable Power Venter Power Venter Tee With Drip Leg Cleanout Cap At Lowest Point Of Vent Sy...

Page 17: ...10 6 9 06 8 07 7 36 6 80 6 23 5 80 5 52 4 96 4 53 4 11 3 82 1 1 4 1 380 1400 950 770 660 580 530 490 460 430 400 360 325 300 280 35 39 6 26 9 21 8 18 7 16 4 15 0 13 9 13 0 12 2 11 3 10 2 9 20 8 50 7...

Page 18: ...ng its full rated capacity as specified in Table 6 A field LP tank regulator must be used to limit the supply pressure to maximum of 14 W C 3 5 kPa All piping should be sized in accordance with the la...

Page 19: ...t Not standard equipment Also refer to Electrical Section Never use an open flame to detect gas leaks Explosive conditions may exist which would result in personal injury or death START UP Open the ma...

Page 20: ...ion Box 7 Pilot Tubing 9 High Limit Switch 10 Pilot Burner Assembly 11 Blocked Vent Spill Switch These safety devices are located on the rear header plate of heat exchanger inlet air side This safety...

Page 21: ...exceed 90 seconds from a cold start Make sure your fan is functioning properly 4 The wall thermostat is a temperature sensitive switch which turns the main gas valve ON or OFF to control the temperat...

Page 22: ...ressure to the main burners f Manual shutoff valve for service and long term shut down Separate from the automatic valve on some models 2 The high limit switch interrupts the flow of electric current...

Page 23: ...of the Heat Exchanger Air Inlet Side 14 Blocked Vent Spill Switch Located in the Upper Right Corner of the Unit Access Side Figure 19 Burner Components IntermIttent Pilot Ignition Also refer to Figure...

Page 24: ...3 5 inches W C 0 9 kPa Adjustment of the pressure regulator is not normally necessary since it is preset at the factory However field adjustment may be made as follows a Attach manometer at pressure t...

Page 25: ...e operation of the gas duct furnace The gas valve should close tightly completely extinguishing the flame on the main burners 11 Check the operation of the pilot safety device by closing the pilot lin...

Page 26: ...Figure 23 Burner Assembly Parts Figure 21 Duct Furnace Components Figure 22 Burners Controls FLAME CARRYOVER MAIN BURNER PACKAGED GAS VALVE BURNER DRAWER PILOT BURNER ASSEMBLY PARTS PILOT OBSERVATION...

Page 27: ...BRACKET JUNCTION BOX 9 SCREW S T 10 SCREW MACHINE L 3 4 11 NUT KEPS EXT LOCKWASHER 12 AIR PRESSURE SWITCH 13 DRILL SCREW 14 JUNCTION BOX ASSEMBLY REF NO DESCRIPTION 15 SNAP BUSHING 16 RELAY 17 STRAIG...

Page 28: ...from the Power Venter Blower Housing Item 8 6 Remove the Blower Wheel Item 9 from the motor shaft by removing the set screw Item 14 using a 1 8 Allen Wrench 7 Remove the three Motor Mounting Nuts Item...

Page 29: ...piping is inadequately sized Refer to Installation 5 Clean pilot orifice Refer to Oper ation 6 Eliminate drafts Refer to Installation 7 Refer to Installation 1 Open all manual gas valves 2 Replace fus...

Page 30: ...s valves 2 Increase size of pilot flame Refer to Operation 3 Purge air from gas supply 4 Follow lighting instruction label adjacent to gas valve 5 Remove pilot orifice Clean with compressed air or sol...

Page 31: ...2 Replace motor 3 Check for 24V across 1 and 3 terminals on fan relay If 24V is present jumper terminals numbered 2 and 4 If motor runs the relay is defective and must be replaced If 24V is not prese...

Page 32: ...tor voltage with fan running Should be 115 volts AC 3 Refer to Operation 1 Close thermostat contacts 2 Check for 24V across 24V terminals of S8600 3 Set gap to 0 1 4 Replace pilot assembly 1 Check all...

Page 33: ...ing removal or reinstallation of the defective Product or parts thereof c to any damage due to corrosion by chemicals including halogenated hydrocarbons precipitated in the air d to any workmanship of...

Page 34: ...34 NOTES...

Page 35: ...e controls GAS EQUIPMENT START UP GENERAL With power and gas off Make certain all packing has been removed Tighten all electrical terminals and connections Check damper linkages for tightness Check al...

Page 36: ......

Reviews: