17
Assembly of the roof-tile
clamps for plain tile
The roof-tile clamp for a roof-mounted assembly with a plain tile covering is also usable for roofs with slate,
shingle and Prefa sheet metal roof systems.
Fixture of the lower lath 24 x 80 x 600 mm with two screws
4 x 50 mm.
If the lath will lie in the area of the main lath, the lath
24 x 80 x 600 does not apply.
The roof-tile bracket has to be adjusted in a way that only one
tile has to be grinded. Vertically, the roof has to be adjusted in
a way that one capping tile has enough space for not having
to be grinded.
The roof hook will be fixed with two screws 5 x 60 mm. The
roof-tile bracket must not lie on the tile or leave pressure marks
on it.
Tile the complete brick laterally.
Grind the brick and tile the roof afterwards.
Tile the roof with all the remaining bricks.
Any other roof-tile clamps have to be lined up in a row.
1410004 Roof-tile bracket V2 plain tile
completely without lead
If the roof-tile bracket will find a too deep lying position, the
delivered lumbers of 5 mm have to be laid unter the hook.
When mountig the field in regions with high snow load
zone of more than 2 kN/m², it is necessary to place
the roof hooks in the rafter area.