12
1
2
3
3
2
1
Assembly preparation - sequence
Single-row collector field
When assembling single-row collector fields, the collectors will be mounted starting with the respectively outer collector.
The exact assembly of the collectors will be described starting with page 29.
Assembly sequence
or
Single-row collector field
Multi-row collector field
When assembling mulit-row collector fields, the collectors which are located one above the other will be mounted first of
all. After placing the first collector, the second collector will be adjusted above the first one. The collectors which are lying
one above the other have to be aligned accurately. The exact assembly of the collectors will be described starting with
page 32.
Multi-row collector field
Summary of Contents for FKF 200
Page 1: ...Assembly instructions Solar collectors FKF 200 240 270 Roof integrated installation...
Page 43: ...43 Initial operation Schematic drawing of the system construction and piping scheme...
Page 44: ...44 Initial operation Schematic drawing of the system construction and piping scheme...
Page 45: ...45 Notes Initial operation...
Page 46: ...46 Notes Initial operation...