Assembly of the solar collectors
Placement of the first collector.
The exact alignment and fixation happens after laying on and
connecting of all collectors.
Uncovered roof area with construction lath.
Fixation with chipboard screws (3 pieces per lath).
Before the following collector can be layed down the hydraulical
collector connector must be mounted at the concisely
overhanging collector connection.
1300002 collector connection set hydraulical
Insert the hydraulical collector connerctor into the manifold. Pay
attention that both O-rings are mounted. Push the connector all
the way to the stop and secure it with the spring lock.
At the upper as well as at the lower collector connection the
hydraulical collector connector will be pre-assembled according
to the image alongside.
Summary of Contents for FKF 200
Page 1: ...Assembly instructions Solar collectors FKF 200 240 270 Roof integrated installation...
Page 43: ...43 Initial operation Schematic drawing of the system construction and piping scheme...
Page 44: ...44 Initial operation Schematic drawing of the system construction and piping scheme...
Page 45: ...45 Notes Initial operation...
Page 46: ...46 Notes Initial operation...