4
Operation
Particle filter system
In addition, very low ambient temperatures
may prevent a sufficiently high exhaust gas
temperature being reached. This causes
the regeneration process to be disrupted.
The soot filtered out of the exhaust gas
then collects in the particle filter, as it is not
burned off during the continuous regeneration
process. In this case, a parked regeneration
of the particle filter must be performed. This
regeneration process, which takes approx. 30
minutes, can only be performed when the truck
is stationary, meaning the truck cannot be
used during this time. The driver is informed of
the need for a parked regeneration in advance
by means of corresponding messages on the
display and operating unit. Details of these
messages are provided in the chapter entitled
"Messages regarding parked regeneration on
the display and operating unit".
Interrupting parked regeneration
Releasing the parking brake during parked re-
generation interrupts the parked regeneration
process.
In the display and operating unit, the following
message appears:
PARK. REG. ERROR
.
NOTE
If regeneration is interrupted too frequently,
additional engine maintenance may be
required from the authorised service centre.
– Apply the parking brake.
– Restart parked regeneration.
The restarted parked regeneration requires
another 30 minutes to complete, no matter
how complete the interrupted parked regener-
ation was.
If the display message
PARK. REG. ERROR
appears more than twice in succession
without the parking brake being released
during parked regeneration, there may be a
malfunction in the internal combustion engine.
– Notify the authorised service centre.
184
57348011800 EN - 11/2018
Summary of Contents for RX70 Series
Page 2: ......
Page 4: ......
Page 13: ...1 Foreword ...
Page 21: ...Foreword 1 Your truck 57348011800 EN 11 2018 9 ...
Page 38: ...1 Foreword Environmental considerations 26 57348011800 EN 11 2018 ...
Page 39: ...2 Safety ...
Page 53: ...Safety 2 Residual risk 57348011800 EN 11 2018 41 ...
Page 71: ...3 Overviews ...
Page 83: ...4 Operation ...
Page 321: ...5 Maintenance ...
Page 328: ...5 Maintenance General maintenance information 316 57348011800 EN 11 2018 ...
Page 330: ...5 Maintenance General maintenance information 318 57348011800 EN 11 2018 ...
Page 334: ...5 Maintenance General maintenance information 322 57348011800 EN 11 2018 ...
Page 378: ...5 Maintenance Remaining ready for operation 366 57348011800 EN 11 2018 ...
Page 379: ...6 1000 hour maintenance annual mainte nance ...
Page 383: ...7 Technical data ...
Page 391: ...Technical data 7 Ergonomic dimensions 57348011800 EN 11 2018 379 ...
Page 394: ...7 Technical data Fuse assignment 382 57348011800 EN 11 2018 ...
Page 404: ......
Page 405: ......
Page 406: ...STILL GmbH 57348011800 EN 11 2018 ...