Striem
3100 Brinkerhoff
Kansas City, KS 66115
Tel: 913-222-1500
Fax: 913-291-0457
www.
striemco.com
Made in the U.S.A
OS-15
Cover
(included with
base unit)
Riser Kit
OS-25
VENT
FLOW
Figure 4
Finished floor
Fasten Cover
Install Riser
VENT
FLOW
Figure 1
Remove cover
Install ring / bolts
Finished floor
X"
VENT
FLOW
Figure 2
Finished floor
Install
Riser
Measure
X"
Figure 3
Riser
Mark, cut,
and deburr
Measurement from
Figure 2
Riser
Bolts
Gasketed Ring
SR16 Riser Kit
(Sold Separately)
2-1/8" Min.
VENT
FLOW
Figure 5
16" Max.
VENT
FLOW
Tools included (with riser kit)
Silver permanent marker
•
Tools Needed:
Tape measure
•
Phillips head screwdriver
•
Jigsaw or
•
Cordless circular saw or
•
Reciprocating saw
•
Riser Assembly Instructions/Steps:
If unit is to be buried, you will need a riser kit (sold separately). The 16 Series TeleGlide Riser System for these models
1.
allows riser heights from 2-1/8" above standard unit up to 16". Only ONE riser may be used per base unit to allow sufficient
access to internal serviecable components. See Figure 5.
If more than 16" of riser height is needed, you will need to adjust jobsite requirements OR purchase the next available
2.
model with a 24 Series TeleGlide Riser System which allows taller riser heights.
Once unit is set so that pipe connections line up with jobsite piping, remove cover from unit. Fasten yellow gasketed ring to
3.
unit with hardware provided in separate riser kit. Ring flange with 4 bolt notches faces down against the unit. See Figure 1.
Push riser into ring until it stops (about 1 inch). See Figure 2.
4.
Measure the distance from the top edge of the riser down to the finished floor. Make sure to account for any future tile work
5.
in your measurment. See Figure 2.
Remove riser from ring. Take measurement from step 5 from the BOTTOM of the riser upwards towards the top of the
6.
riser. Mark a line around the riser, and cut with handsaw, jig saw, or reciprocating saw. Remove debris from cut edge with
scraper, utility knife, or gloves. See Figure 3.
Place cut riser back into ring on unit until it stops. Fasten cover from unit into riser with the same 4 bolts from the unit. Unit
7.
is ready to be water tested and backfilled. Install finished floor. See Figure 4.
TeleGlide Riser (16 Series) Installation Guidelines
(OS-15, OS-25)
Minimum and maximum riser heights when units are buried.
OS & OCT SERIES INSTALLATION,
OPERATION AND MAINTENANCE GUIDE
ECO:
8/16/18
MJ
REV:
DATE:
DWG BY:
DESCRIPTION:
PROPRIETARY AND CONFIDENTIAL
THE INFORMATION CONTAINED IN THIS DRAWING IS THE SOLE PROPERTY OF
STRIEM, LLC.
ANY REPRODUCTION IN PART OR AS A WHOLE WITHOUT THE WRITTEN PERMISSION OF
STRIEM, LLC.
IS
PROHIBITED.
NOTES:
Striem oil separators are rated and manufactured with an internal flow control system already in
place. They do not require an external flow control system or air intake vent.
Striem oil separators are not to be installed in any other manner except as shown. Consult local
codes for separate trapping requirements, cleanout locations and additional installation instructions.
SHEET NUMBER: