Starting up
5 — 5
09_0150_0802GB
Carry out a test run before operating the machine.
The following conditions must be met before the machine is switched
on:
-- The machine should be in a horizontal position.
-- The machine must be connected to a suitable power supply. Read
the ”
Electrical connection
” section in the chapter ”
Transport, Set-
up and Connection
”.
For the test run, you must switch on and inspect the machine.
Note
Any defects found during these tests must be rectified immediately.
A fresh inspection is necessary after every repair. The machine may
only be put into operation once all the inspections described below
have been concluded satisfactorily.
A different control cabinet may be fitted to the machine, depending
on the model.
The machine is switched on at the main switch.
1
2
Item
Designation
1
”Machine ON” main switch
2
”Machine OFF” main switch
Continued next page
5.2
Test run
Switch-on conditions
5.3
Switching on the
machine
with main switch