TECHNICAL PASSPORT, INSTALLATION AND MAINTENANCE INSTRUCTION

 

distributor  (9)  (Fig.  1),  would  be  lifted  more  easily.  We  also  recommend  oiling  the  closing 
door  hooks.  Sometimes,  it  needs  to  be  checked  if  the  doors  seals  uniformly.  In  order  to 
make doors seal uniformly, gasket needs to be changed or lock tabs need to be adjusted.  

 

SAFETY EQUIPMENT REQUIREMENTS 

Boiler room is a zone of increased hazard. Irresponsible behaviour can lead to injuries, 
poisoning, fire, damage to boiler or the heating system.  

 

Safety requirements and warnings

 

 

         Consequences for not adhering to the safety   requirements 

and instructions

 

 

1. Do not let the water in boiler reach the 
boiling point. Do not fire the boiler without 
water. Do not let the pressure of system 
exceed 1,5 bar. 
Do not freeze the water in the boiler or 
heating system.

 

 

1. After water boils out, boiler will overheat and crack up. If 
temperature is rising in the boiler without known reason, immediately 
close the top air supply valve, lift the air distributor, set the water pump 
to maximum speed, open the door while keeping your face away and 
load sand, dirt or other inflammable material. 

 

 

2. Boiler room ventilation is necessary.

 

 

    2. Boiler operates poorly.

 

3. Do not allow air in trough the bottom door and do 
not ignite fuel from the bottom.

 

 

3. Condensate will leak, you will use up more wood. Water in boiler will 
start to boil and coal will fall out. 

 

4. Do not store fuel inside boiler (after loading the 
firewood it has to be ignited).

 

4. Firewood will ignite from leftover ember at the bottom and 
will burn out while leaving condensate and raisins. 

 

   5. While boiler is burning do not lift the air distributor.

 

 

 

5. If you hit air distributor, which has softened from heat, against the 
firewood you will bend it and if it will stick deeper into fuel its lifespan 
will be reduced significantly. 

 

 

Most common installation mistakes

 

                                Consequences                                          

Troubleshooting 

 

 

1. Installed using other boiler manufacturer diagrams. 

 

 

 
1. High flow cools the walls of combustion chamber and smoke 
opening enough for humidity to appear. When boiler is heated, 
humidity disappears, but it makes the ash stick to the walls and 
therefore boiler and flue becomes clogged up periodically. 

 

Recommended flow must be achieved 

– moisture will 

accumulate at a lower point than centre of combustion 

– 

smoke openings will stay clean. 

 

 

2. Circulation pump, together with boiler, is installed 
in on old gravity circulation system, which has no 
element adjustment

 

2.

 

Large amounts of condensate are produced because of high 

flow of cold water, boiler room will acquire poisonous smell of 
condensate. Boiler works very inefficiently and it lacks power. 
Balance tap must be installed before boiler, or boiler room should 
be built according to figure 7 diagram.

 

 

 

Most common operation mistakes 

 

                                                   

Consequences   

Troubleshooting 

 
 
 

 

 1. Boiler is fired while flue draft is too high. 

 

 

1. Pulsation can be heard in a boiler. Air valve sometimes jumps. 
Boiler operates very inefficiently - condensate is leaking and 
there is a lack of power. 

 

Extraneous air must be supplied through the flue ring. If your boiler has 
no flue connecti

on, you will only have to do “U” form cut in a sill and 

gradually unbend this newly created plate until the boiler starts working 
normally. Alternatively, you can install a draught regulator.

 

 2. Lifting cord of air distributor is not oiled.  

 

   

2. Air distributor is difficult to lift, cord wears excessively. 

 

Must be lubricated using WD - 40. 

 

 

 3. Plastic material, cardboard boxes are being 
burnt in the boiler. 

 

3. Cardboard boxes obstruct the burn and burning plastic package 
leftovers is dangerous, because produced gasses cannot burn 
evenly quickly, and excessive gasses explode inside chimney and 
damage the connections of the flue. 

 

Summary of Contents for BIO S10 U

Page 1: ...STROPUVA TECHNICAL PASSPORT INSTALLATION AND MAINTENANCE INSTRUCTION Solid fuel boiler for central heating...

Page 2: ...ther boiler water heater and floor heating 13 6 3 Connection diagram of Stropuva boiler to another boiler water heater radiator floor heating 14 6 4 Connection diagram of Stropuva boiler to another bo...

Page 3: ...m2 1 1 MAIN TECHNICAL SPECIFICATIONS Fuel used firewood wood residue sawdust briquettes peat briquettes coal pellets Recommended fuel moisture up to 30 Model of boiler S7 S10 S12 S20 S30 S40 S7 BIO S1...

Page 4: ...ound and the chimney mm 991 1413 5 1302 1550 1285 1549 991 1413 5 1302 1550 1285 1549 1494 1302 1673 5 1285 1664 Dimensions mm 1900 1900 1900 1900 1900 1900 h d 1330 450 1900 450 1700 550 2100 550 170...

Page 5: ...arger diameter steel cylinder which provides thermal insulation Heated water resides between these two cylinders There is a draft regulator on the front side of the boiler 2 see 7 3 The construction h...

Page 6: ...rpose is to correctly distribute air in generation zones located below and next to air distributor as well as in combustion zones located near and above the distributor Air distributor 9 Fig 1 rests u...

Page 7: ...at the bottom of the boiler inside the lower doors 11 Fig 1 Fire grates 19 Fig 1 Fig 7 can be found by opening the ash removal doors 11 Fig 1 This part is attached in U boiler for additional air to go...

Page 8: ...boilers from overheating When water pressure reaches critical levels the valve opens up releasing the heated water into the sewerage at the same time adding cold water through the automatic system Va...

Page 9: ...nless steel will have to be used Rectangular liners are not as reliable because openings caused by temperature changes appear at the connections Boiler is placed directly on concrete floor When carryi...

Page 10: ...ple and proven diagrams We don t recommend building accumulative heat tanks because our boiler is more efficient while working in preservation mode than while charging accumulative tank in maximum pow...

Page 11: ...11 TECHNICAL PASSPORT INSTALLATION AND MAINTENANCE INSTRUCTION 6 HEATING SYSTEM DIAGRAM Figure 10 Stropuva...

Page 12: ...warmer than selected value Thanks to this pump P water loudly circulates through coil pipes F of floor heating also flows to boiler through distribution valve T 3 20 50 which when water from radiator...

Page 13: ...atic valve 1 pcs 7 Circulation pump installation kit D25 1 pcs 23 Valve 1 5 bar 1 pcs 8 Separable connection D25 V i 2 pcs F to out of floor heating 9 Automatic bleeding device 1 pcs B to out of water...

Page 14: ...cs 21 Adapter D32 x D25 2 pcs 7 Circulation pump installation kit D25 1 pcs 22 Thermostatic valve 1 pcs 8 Separable connection D25 V i 2 pcs 23 Valve 1 5 bar 1 pcs 9 Automatic bleeding device 1 pcs F...

Page 15: ...lbow D25 x D15 3 pcs 18 Filling valve i i 1 2 1 pcs 7 Circulation pump installation kit D25 8 Separable connection D25 V i 1 pcs 2 pcs 19 Release valve 1 2 20 Brass disc valve V V 1 21 Adapter D32 x D...

Page 16: ...ets and sawdust briquettes immediately ignite so that the load of fuel would not be ignited by leftover ember Before igniting the boiler carefully read the instruction of traction regulator see sectio...

Page 17: ...all down to the bottom Coal load must not be larger than up to the fuel loading door 8 Fig 1 Put firewood about 2 kg on top of coal and ignite it After ignition switch valve 6 Fig 1 must be lifted of...

Page 18: ...disappears see Fig 10 c If fuel is burning well but temperature increases very slowly and there is condensation leaking out of flue it means that the flow of heated water going through boiler is exces...

Page 19: ...ll stick deeper into fuel its lifespan will be reduced significantly Most common installation mistakes Consequences Troubleshooting 1 Installed using other boiler manufacturer diagrams 1 High flow coo...

Page 20: ...diagrams According to Figure 10 we recommend connecting gravity controlled radiator a radiator without thermos valve Hot water goes through balance tap bk1 Fig 10 to the nearest radiator which can wor...

Page 21: ...ts No need to move the boiler and repeatedly connect to the chimney or heating system Usually no need to make changes in the heating system This solutions allows a complete automatization of firing pr...

Page 22: ...fuel boiler STROPUVA 1 pcs Safety pressure valve 1 5 bar 1 pcs Thermometer 1 pcs Deflectors 2 pcs Air injection collector 1 pcs Air distributor 1 pcs Fire grate 1 pcs Technical passport 1 pcs PACKAGE...

Page 23: ...c procedures inspection of boiler and control elements at least once a year To preserve warranty agreement and its entries We recommend that the installation assessment the first start up adjustment o...

Page 24: ...aris Trak distr LT 25144 Lithuania tel 370 525 51763 Boiler model Product number Date of sale Signature Stamp SELLER Date of sale Signature Stamp PERSON RESPONSIBLE FOR INSTALLATION Installation addre...

Page 25: ...e Surname Signature The boiler has a year warranty If the heat exchanger is broken seller has to fix the boiler on its own expense but if other components are broken not due to the fault of the end us...

Page 26: ...JSC Stropuva ir ko company code 300149972 K stu io g 1A Lentvaris Trak distr LT 25144 Tel 370 5 255 17 63 mob 370 656 08961 www stropuva lt info stropuva lt...

Reviews: