STULZ UltraWater 3-stage reverse osmosis system SUW
Installation
© STULZ GmbH, Hamburg
- 21 -
7.
INSTALLATION
7.1. Assembly
Minimum space of 5 cm should be left on all sides of the installation board, to allow room for the connec
-
tions.
The spacing of the mounting holes is 550 mm horizontally and 380 mm vertically.
The pressure tank should be installed close to the system. The position of the tank (standing, lying) is un
-
important. The tank should not be placed more than 2 m higher or lower than the system.
To ensure safe operation of the system, the erection standards of DIN VDE
100 must be complied with.
If the equipment is installed in an environment in which no leakage must
occur, a water detector should be installed at a suitable location. This must
then cut off the water supply pipe in the event of a fault. In addition, a col-
lecting basin should be installed beneath the equipment.
Note:
The ambient temperature should always lie b5 and +35°C during operation. The stor
-
age temperature is 4 to 45°C.
Secure the tank so it cannot fall!
Note:
Choose the fastening materials in accordance with the local conditions.