7
Workshop manual
XJ 25 - 110, XJC 50 - 110, XJS 25 - 110
Standard version
AquaTronic version
XJC
2.
Service inspection
2.1
Service Data Kit
Contact Sulzer.
2.2
Pump start and cable check
Check the cable for damage and that there is no water or corrosion in the connecting plug.
Test the insulation between cable end / plug and earth.
Check if the pump starts by connecting it to the power supply.
2.3
Dismantling cover
Unscrew and lift off the cover and disconnect the power cables from the contactor/terminal block.
If the water has penetrated through the cable gland and the cable seal, the cable gland and the cable seal should be re-
placed. Remove strain relief clamp prior to unscrewing cable gland body. Pull out cable, cable gland, washer and unscrew
the cable seal.
c
DANGER! Always check that the pump is disconnected from the electric power supply
before opening any part of the pump.