1. Floor section Summer Garden Buildings – Hipped Summerhouse 270
Prepare a level area for the Summerhouse to sit. Lay the floor panels upside down and secure them together using 5 x 50mm screws per join as shown.
Important note
To "VALIDATE" the guarantee, adequate provision must be made to ensure ground contact is avoided and air is able to circulate underneath the building.
Placing the building on a concrete pad or slab base is acceptable provided that the building is not allowed to sit in pooled water during wet conditions. If the
building is to sit on soil or grass it MUST be erected on pressure treated wooden 50mm x 50mm or similar bearers (These are not supplied in the kit). We
recommend using pressure treated bearers with all buildings on any type of base.
50mm
50mm
2.Wall panels
Position a back panel and a side panel on the floor as shown. Note how the panel frames sit on the floor with the panel cladding overhanging the floor edge. Ensure square and
secure using 3 x 50mm screws, screw through the frame of the side panel into the frame of the back panel. Position the small back panel next to the first, ensure level and secure
them together using 3 x 50mm screws, screw through the frame of the second panel into the frame of the first. Continue adding the rest of the panels as shown in the
diagrams using 3 x 50mm screws per join.
It is recommended to drill pilot holes with a
3mm
3mm drill bit for all screws in this section.
Drill
50mm
Back panels
Side panel
Back panel
50mm
Panel frames
Panel cladding
rest on floor.
overhangs floor
Front panels
edge.