Mounting the Clamp Champ
1. The Clamp Champ comes complete with
three to nine jack bars. Depending on pipe
size and the fit-up, two jack bars and the
main block may be adequate for most fit-up
jobs.
2. Remove Clamp Champ from carrying case
and spread out on a table. To add jack
bars, slide the chain through the opening in
jack bars and loosely tighten chain attach-
ment screw.
NOTE -
Jack bars should be facing same
direction as the main block.
3. Estimate location of jack bars to fit on the
pipe in a 4, 8 and 12 o'clock position (if
using 2 jack bars and the main block) or 3,
6, 9 and 12 o'clock position when using
three jack bars. Before mounting tool,
make sure there is ample thread length on
the chain adjustment shaft so that slack can
be taken out of the chain.
4. While holding main block and chain adjust-
ment handle in one hand and the end of the
chain with the other, wrap the pipe end with
the Clamp Champ. The main block should
be located at the top of the pipe.
(See photo top right)
5
Step 4
5. Attach the chain to the main block and
remove slack by tightening the chain
adjustment. (
See below)
Step 5
OPERATING PROCEDURES
Sumner Clamp Champ, Operator’s Manual
ARC WELDING SUPPLIES - 07 847 7870