Installation Procedure
7
Remove Selected Parts
1. Remove the front and rear doors of the chassis.
Remove the side panels if they are accessible. This modification can be performed
through the front and rear of the chassis if necessary.
Note –
For this installation procedure, the front of the chassis contains system
boards 8 through 15, and the rear of the chassis contains system boards 0 through 7.
2. Remove all peripherals, hub, AC Sequencer, input cables, Remote Power Control
Modules (RPCM), and glove box (if installed) from the peripheral rack area.
3. Remove the trim panels on the sides opposite the existing power shelves.
Leave the brackets in place.
4. Set aside the existing hardware for use in reassembly.
Remove and Install Power Cables, and
Install Ground Cables
1. Install labels “POWER GRID A” to the upper inside of the existing power shelves
(
The labels must also be placed so they are visible when the inside of the chassis is
viewed from the front or back.
2. Remove the existing power cables (red jacket) from four horizontal connectors (J1,
J2, J9, and J10) of the existing power shelves (
Hold the screw locks in place with the 3/16 inch wrench while you remove the
connector screws (
). If the screw locks are not held with the wrench, the
loose hardware could fall inside the power shelf where it is difficult to recover.
Discard these cables, they are not needed.