5. Assemble FOSC housing
5.1
Put desiccant into FOSC
5.2
Put FOSC cover on base directly.
5.3
Install plastic hoop between FOSC cover and the base, tighten hoop
locking system, which is to be fixed by hoop fixing bolt then.
5.4
All nuts (plastic ones) of base need to be re-tightened once more.
6. The installation and fixed of FOSC
6.1
Aerial application: Fix metal hoop and transom to the pole. Please refer to
figure
6
6.2
Wall mounting application: Fix the bracket on the wall with the bolt. (Metal
hoop is not required.) See
figure
7
6.3
Underground application: Metal hoop is not required wall accessories.
SHANGHAI SUN TELECOMMUNICATION CO., LTD.
Building No.145 Lane 666, Xianing Rd.
Jinshan Industrial Zone, Jinshan District
ShangHai, China 201506
Tel: +86 21 60138638
Fax: +86 21 60138635-401
E-mail: ics@suntelecom.cn
http://www.suntelecom.cn
Figure 6
Figure 7