Additionally, the following requirements should be met when the MV Station is placed on
the ground:
Place the MV Station carefully and gently. Do not pull or push the MV Station on any
surface.
The place should be firm and flat with good drainage and no obstacles or outshoots.
The MV Station should be supported by the four feet.
5.2
Hoisting the MV Station
5.2.1 Safety Precautions
Observe the safety operating rules of the crane at all times.
Standing within 5 to 10 meters away from the hoisting areas is strictly prohibited!
Anybody standing under the boom or MV Station is strictly prohibited in the whole
hoisting process.
The hoisting work must be stopped on violent weather days. For example, in strong
wind, heavy rain, or thick fog conditions.
Please observe the following items:
All safety requirements must be met.
A professional instructor is required in the whole hoisting process.
All the used slings must have the load-bearing capacity of at least 30t.
The crane should have sufficient arm length and radius of gyration.
All the connection point must be firmly connected.
The length of the slings can be adjusted appropriately according to on-site conditions.
Transport the MV Station in a level, smooth, and steady way.
Transport the MV Station by connecting the four top corner fittings.
Some accessories may be required to ensure the safety during hoisting.
The following figure illustrates the hoisting operations. Circle A describes the work areas of
the crane. Anybody standing inside the circle B is prohibited for safety considerations.