User Manual
68
8.1.2 Dismantling the Inverter
Risk of burn injuries and electric shock!
Do not touch any inner live parts for 10 minutes after disconnecting the
inverter from the utility grid, the PV inputs and the battery module.
1.
Refer to “
” for the inverter disconnection of all
cables in reverse steps.
2.
Dismantle the inverter referring to “
” in reverse
steps.
3.
If necessary, remove the wall-mounting bracket from the wall.
4.
If the inverter will be reinstalled in the future, please refer to “
” for a proper conservation.
8.1.3 Disposing of the Inverter
Users should take the responsibility for the disposal of the inverter.
Some parts and devices of the inverter, such as the LCD display,
batteries, capacitors, may cause environment pollution.
Do not dispose of the product together with household waste but in
accordance with the disposal regulations for electronic waste
applicable at the installation site.
8.2 Decommissioning the Battery
Decommission the battery in the system after the inverter is decommissioned,
following the steps for a Li-ion battery or lead-acid battery below. SUNGROW is
not liable for disposal of the battery.
8.2.1 Disconnecting Li-ion Battery
1.
Disconnect the DC circuit breaker between the battery and the inverter.
2.
Disconnect the communication cable between the battery and the
inverter.
3.
(Optional)
Turn off the switch on the battery if applicable.
4.
Wait about 1 minute and use the multimeter to measure the port voltage
of the battery.
5.
If the battery port voltage is zero, disconnect the power cables between
the battery and the inverter.