3 Commissioning
19
3.2
Commissioning Procedure
Before starting the inverter, make sure all the installation and connections are
completed and verified. Proceed as follows to start the inverter for the first time.
1.
Connect the AC circuit breaker.
2.
Connect the DC circuit breaker between the inverter and the battery pack.
3.
(Optional)
Turn on the switch on the battery pack manually if the battery is
equipped with a switch (such as LG Li-ion battery, Pylon Li-ion battery and
lead-acid battery).
4.
Rotate the DC switch to “ON”. The DC switch may be integrated in SH5K or
installed by the customer.
5.
The LCD screen will be activated 5s later and enter the initial settings.
6.
Refer to
Fig. 3-1
for button operations and complete all initial settings
according to the procedure in
Fig. 3-2
.
7.
Check the icons on the main screen. Refer to
Tab.
4-1
for the explanations.
8.
Check the state of LED indicators.
Tab. 3-2
State Descriptions of LED Indicators
LED Label
LED State
Description
“RUN”
On
The inverter is running normally.
Blinking
The inverter is in the process of starting.
Off
Other states except Running and Starting.
(Refer to
Tab. 4-1
for state descriptions.)
“FAULT”
On
Permanent fault or upgrade failure.
Blinking
Other system faults or main alarms.
Off
No fault occurs.
9.
Visit
www.solarinfobank.com
or SolarInfo Moni APP to view inverter
information. Get the related manuals at
www.sungrowpower.com
.
If the inverter commissioning fails,
Press
to view the current faults. Remove the
existing malfunctions and then repeat starting up the inverter according to the
procedure detailed in this section.
Summary of Contents for SH5K
Page 1: ...SH5K QUEN Ver14 201708 Version 1 4 Quick User Manual SH5K Grid Connected Hybrid Inverter ...
Page 2: ......
Page 4: ...II System Overview ...
Page 5: ...III ...
Page 6: ...IV ...
Page 7: ...V ...
Page 8: ...VI ...
Page 9: ...VII ...
Page 10: ...VIII ...
Page 32: ...3 Commissioning Quick User Manual 20 Fig 3 2 Initial Settings ...