6. COMMISSIONING
6.1. Start-Up / Shutdown Procedure
The inverter must be installed by a qualified / licensed electrical engineer in accordance to the
countries wiring regulations.
Before switching on, the installation engineer must have completed the Earth Bond, RCD and
earth leakage tests, checked that the solar panel Voc voltage does not exceed 480V and
checked the battery voltage.
Power ON Sequence:
1. Switch on AC
2. Press Start Button
3. Switch on Battery and battery breaker
4. Switch on the DC (PV Isolator
Shutdown Sequence:
1. Switch off AC
2. Press the start button
3. Switch off the battery and the battery breaker
4. Switch off the DC (PV isolator
Summary of Contents for SUN-25K-SG01HP3-EU-BM2
Page 19: ...Page 19 Hybrid Inverter Installer Manual 4 4 1 Function Ports Definition ...
Page 26: ...Page 26 Hybrid Inverter Installer Manual ...
Page 27: ...Page 27 Hybrid Inverter Installer Manual ...
Page 29: ...Page 29 Hybrid Inverter Installer Manual 4 10 Wiring System for Inverter ...
Page 30: ...Page 30 Hybrid Inverter Installer Manual 4 11 Wiring Diagram ...
Page 31: ...Page 31 Hybrid Inverter Installer Manual ...
Page 32: ...Page 32 Hybrid Inverter Installer Manual 4 12 Typical Application Diagram of Diesel Generator ...