Page | 70
Hybrid Inverter | Installer Manual
6.2. Information for Commissioning the Inverter
After you have successfully powered up the inverter, it must be programmed and set up as per
the programming feature above.
Check each bond on
the solar panels
Check the VOC does
not exceed 480V
Ensure both MPPTs
are balanced
Measure the sup-
ply voltage check it
matches the settings
of the inverter
If it falls out of the set-
ting range it will cause
the inverse shut down
and alarm
See Grid Setup page
Check the battery
charge and discharge
is within the C rating
of the battery. Too
high will damage the
battery
Check the battery
BMS is communicat-
ing with the inverter
This is the heart of the
system this controller
everything
Ensure you are fa-
miliar with this, if you
fully understand the
controller you will fully
appreciate the capa-
bilities of this inverter
See section ‘Program
Charge / Discharge
Times’
This is for paralleling
systems (Under De-
velopment), and wind
turbine
If paralleling inverters
in 3 Phase check you
phase rotation before
switching on the AC
Load, in 3 Phase the
output voltage will in-
crease across phase
to 400V
If using a wind turbine
please ensure you
have the correct limit-
ing resistor, caps and
rectifier
Familiarize yourself
with common fault
codes
Summary of Contents for SUN-25K-SG01HP3-EU-BM2
Page 19: ...Page 19 Hybrid Inverter Installer Manual 4 4 1 Function Ports Definition ...
Page 26: ...Page 26 Hybrid Inverter Installer Manual ...
Page 27: ...Page 27 Hybrid Inverter Installer Manual ...
Page 29: ...Page 29 Hybrid Inverter Installer Manual 4 10 Wiring System for Inverter ...
Page 30: ...Page 30 Hybrid Inverter Installer Manual 4 11 Wiring Diagram ...
Page 31: ...Page 31 Hybrid Inverter Installer Manual ...
Page 32: ...Page 32 Hybrid Inverter Installer Manual 4 12 Typical Application Diagram of Diesel Generator ...