The distance from an obstacle being at East, South or West must be : 
- at least 1,5 time the height of the obstacle for countries with latitude 30° 
- at least 2 times the height of the obstacle for countries with latitude 40° 
- at least 2,5 times the height of the obstacle for countries with latitude 50° 
 
For optimum performance the collectors must have inclination to the horizon of 45° (countries 
with latitude 40°). In general the inclination of the collectors should be 5° higher than the 
latitude of the place. Any change of the above mentioned condition causes a reduction to the 
average annual gain of usage that must be considered. 
 
The distance between the collectors and the boiler or other heat exchanger must be the shorter 
possible. 
 
 The area of collector’s installation should have an easy and safe access for maintenance. 
 
The static resistance of the surface that the installation will take place must be considered in 
relation with the total weight of the collectors and other parts that will be installed. 
 
The installation should be done according to the electric, plumbing and town planning 
regulations applicable in the installation area. 
 

11.

 

Maximum limit of snow load and wind speed  

It is admitted that our collectors can resist without any failure to a snow load of up to 500 Pa. The 
support systems may only be installed in locations with a value of possible snow load lower than 
500 Pa. According to the characteristics of their support frame and the standard ENV 1991, Solar 
Flame systems may not be installed in locations where the maximal mean wind velocity exceeds 
55 m/s (value for islands exposed to high winds). 
 
12.

 

Installation 

Installation, connections and starting of the system should be made by specialized, 

experienced and authorized technicians as necessary. 

As soon as the support structure is ready to fix the collector/s we have to use the M8 screws 

and flat washers M8. Each collector has 4 receptions for M8 screws (2 on the upper side and 2 on 
the down side) as indicated in the following drawing. After placing the collector on the support 
structure these receptions have to align with the oval holes of the collectors holders. 

Summary of Contents for PK SL AL 2.0

Page 1: ...TECHNICAL PASSPORT INSTALLATION and OPERATION MANUAL For SOLAR COLLECTORS SL AL With full plate aluminum absorber model serial number version 01 SRCC 2 2011...

Page 2: ...against lightning 6 6 COLLECTORS INTERCONNECTING IN A FIELD WITH 20m 6 7 Pressure loss 7 8 Recommended angle of installation of the collector 7 9 Collector protection against frost 8 10 Maintenance 8...

Page 3: ...measures to make them compliant regulations and norms concerning safety installation and operation of solar collectors protective gloves eyewear should be used make sure collector is securely attache...

Page 4: ...stallation user CAUTION Danger of injury damage of system due to incompetent operation The solar collector must be serviced only by persons familiar with the operation manual Structural changes to col...

Page 5: ...osiphonic solar systems or as part of forced circulation central system for heating sanitary water space heating air conditioning and pool heating The collectors PK SL AL are flat solar collectors wit...

Page 6: ...sting or earth them to an earth rod using wire of the same size The route of this wire should be always outdoors Ask specialist for more information 6 COLLECTORS INTERCONNECTING IN A FIELD WITH 20m Fo...

Page 7: ...lace plus 5 At this angle the maximum of the year around efficiency is achieved In case of difficulty to follow the above rule try to keep the inclination between 30 and 50 in order to benefit a minim...

Page 8: ...stallation is near electrical wires keep safety distance minimum 5 meters and pay maximum attention when handing long parts of the support structures or tools for the installation 10 2 Selection of in...

Page 9: ...eight of the collectors and other parts that will be installed The installation should be done according to the electric plumbing and town planning regulations applicable in the installation area 11 M...

Page 10: ...e between them must be kept at the minimum The system of collectors should be connected to the hot water tank heat exchanger of the tank with tubing properly insulated When installing collectors in pa...

Page 11: ...ticeable defects at the moment of purchase in which case the customer must make the claim at the shop immediately after noticing the defect as it is provided for in the general conditions of sale 14 2...

Page 12: ...ether the claim has grounds or not and whether the defect is within the scope of the warranty set forth in this certificate for limited warranty after which informs the customer as to its decision 14...

Page 13: ...aterial of solar glass K Heat tempered prismatic glass Material of pipes F Copper Absorber pipes pcs diameter G 9 x 8 11 x 8 Manifold pipes pcs diameter 2 x 22 Inlet Outlet P N 22 Material of absorber...

Page 14: ...l protection regulation 16 2 RECYCLING AND WASTE DISPOSAL At the end of life cycle of each product its components are due to be disposed of in conformity with regulatory prescriptions According to Dir...