START UP PROCEDURE
Bin Control Operation
The bin control is used to shut the machine off when the bin fills with ice. The bin control must be
checked upon installation or initial start-up and when performing maintenance. Adjustments are
not covered under warranty. There is one bin switch for each evaporator. The actuator arm of the
bin switch comes in contact with the splash curtain. When the bin is full of ice, the splash curtain is
held open when ice drops off of the evaporator. This releases the
pressure of the bin switch actuator arm allowing the switch to open.
Bin Control Adjustment
All Models : Check the bin switch for proper adjustment by swinging the
bottom of the curtain away from the evaporator. Slowly bring the
curtain towards the evaporator. The switch should close when the
bottom edge of the curtain is even with the outer edge of the water
trough. Adjust the switch by loosening the nuts that hold the switch in
place. Move the switch to the proper position and retighten the nuts.
Recheck the adjustment. Adjustments are not covered under warranty.