SECTION 03 35 43                                                                 Updated April 6, 2011 

 

D.

 

Pre-installation Meeting: The Contractor shall conduct an onsite pre-
installation meeting with the Owner in which the written floor finishing plan 
is reviewed. Pre-installation meeting shall include a walk down of the floor to 
review the condition of the floor and to determine surface preparation 
requirements. Additional topics of discussion shall include: 
1.

 

Floor surface preparation, cleaning, and protection. 

2.

 

Previous products applied to concrete floors, including curing compounds. 

3.

 

Application means and methods, including equipment to be used. 

4.

 

Sequence of installation. 

5.

 

Location of sample finished area. 

6.

 

Desired sheen and appearance of the finished floor. 

7.

 

Acceptability of finished slab and/or deficiencies of finished slab and 
associated remedies. 

 
 

 
1.05

 

PROJECT/SITE CONDITIONS 

 

A.

 

Floor areas to be polished are to be free and clear of all obstacles including 
racking, fixtures and temporary equipment and materials in order to provide 
an open and uninhibited concrete slab. 

 
B.

 

Any anchoring bolts, cut off conduit and other associated items removed in a 
demolition process need to be removed or recessed a minimum of ¼” below 
lowest surrounding point of the concrete floor surface. 

 

C.

 

All previous flooring materials such as tile, carpet and wood flooring and 
associated adhesives are to be removed prior to the installation of the polished 
concrete flooring.  Caution needs to be taken to ensure that no damage to the 
concrete floor takes place since the slab will be the finish product. 

 

D.

 

A minimum of 28 days of cure on new concrete should be provided before 
system installation is initiated. 

 

E.

 

Protection: General Contractor shall protect areas to receive polished concrete 
finish at all times during construction to prevent oils, dirt, metal, excessive 
water and other potentially damaging materials from affecting the finished 
concrete surface.  Protection measures listed below shall begin immediately 
after the concrete slab is poured: 

1.

 

Protect from all petroleum stains during construction. 

2.

 

Diaper all hydraulic powered equipment.  

3.

 

Do not park vehicles on inside slab.   

4.

 

No pipe cutting machines will be used on inside floor slab. 

Summary of Contents for InovaCrete

Page 1: ...ete Institute ACI 1 ACI 117 Standard Specifications for Tolerances for Concrete Construction and Materials American Concrete Institute 2 ACI 301 Specifications for Structural Concrete for Buildings Am...

Page 2: ...s D Samples Prior to commencement of work provide 10 x 10 finished samples for the Owner s review See 1 06 Mock Up E Provide maintenance procedures for the polished concrete floor to the Owner s Repr...

Page 3: ...de an open and uninhibited concrete slab B Any anchoring bolts cut off conduit and other associated items removed in a demolition process need to be removed or recessed a minimum of below lowest surro...

Page 4: ...s placed for installation of sample it must meet the same specification as the project s flatwork requirements for the polished concrete floor areas B Equipment tooling and products used are to be the...

Page 5: ...a Overall Ff 40 b Local Ff 20 c Overall FL not required d Local FL not required 2 Tight Hard Troweled three passes concrete No burn marks Reference ACI 302 1R class 5 or class 6 floor 3 Curing Option...

Page 6: ...aFlex I SLX 100 Oil repellent sealer by Prosoco J Ameripolish Decorative Dyes by American Decorative Concrete K Prosoco LS Guard Lavina SPS Floor Glow by Prosoco PART 3 EXECUTION 3 01 EXAMINATION A Ve...

Page 7: ...Calibra Ceramic bonded diamond until a uniform scratch pattern is achieved Vacuum the floor thoroughly using squeegee vacuum attachment 4 Continue the process with 100 grit Calibra Ceramic bonded diam...

Page 8: ...mage dust and spatter related to the work of this section 1 Repair damage caused by the work of this section 2 Clean dust and spatter from adjoining surfaces C Advise all contractors vendors and other...

Reviews: