SECTION 03 35 43                                                                 Updated April 6, 2011 

 

5.

 

Do not place reinforcing steel on interior slab, to avoid rust stains. 

6.

 

Do not use acids or acidic detergents on slab. 

7.

 

Inform all trades that the slab is to be protected at all times. 

8.

 

No skids are to remain in contact with floor surface for an extended 
period of time. 
 

 

F.

 

Ensure that adequate lighting has been installed to support surface preparation 
and polishing application. A minimum of half the illumination of an open 
facility is required. 

 
 

 
1.06

 

MOCK-UP 

 

A.

 

Install a completed 10’x 10’ sample of the proposed system at location 
determined by the Owner’s Representative.  If approved by owner or owner’s 
representative, the mock-up may be incorporated into the work.  If a special 
concrete slab is placed for installation of sample, it must meet the same 
specification as the project’s flatwork requirements for the polished concrete 
floor areas. 

 
B.

 

Equipment, tooling and products used are to be the same specified in Section 
2.02 and the same that will be used for the entire project. 

 
 

1.07

 

WARRANTY 

 

C.

 

The installer shall furnish a SINGLE SOURCE warranty for their system for a 
period of one year minimum.   

 
 

1.08

 

ENVIRONMENTAL LIMITATIONS 
 

A.

 

Comply with manufacturers’ written instructions for substrate temperature and 
moisture content, ambient temperature and humidity, ventilation and other 
conditions affecting chemical performance. 

B.

 

Flatness and levelness: 
1.

 

Finish Concrete shall have a minimum Floor Flatness rating of at least 40. 

2.

 

Finish Concrete shall have a minimum Floor Levelness rating of at least 30. 

3.

 

Finish Concrete shall be cured a minimum of 28 days or at which point 
equipment can be put on the slab and does not displace aggregate. 

Summary of Contents for InovaCrete

Page 1: ...ete Institute ACI 1 ACI 117 Standard Specifications for Tolerances for Concrete Construction and Materials American Concrete Institute 2 ACI 301 Specifications for Structural Concrete for Buildings Am...

Page 2: ...s D Samples Prior to commencement of work provide 10 x 10 finished samples for the Owner s review See 1 06 Mock Up E Provide maintenance procedures for the polished concrete floor to the Owner s Repr...

Page 3: ...de an open and uninhibited concrete slab B Any anchoring bolts cut off conduit and other associated items removed in a demolition process need to be removed or recessed a minimum of below lowest surro...

Page 4: ...s placed for installation of sample it must meet the same specification as the project s flatwork requirements for the polished concrete floor areas B Equipment tooling and products used are to be the...

Page 5: ...a Overall Ff 40 b Local Ff 20 c Overall FL not required d Local FL not required 2 Tight Hard Troweled three passes concrete No burn marks Reference ACI 302 1R class 5 or class 6 floor 3 Curing Option...

Page 6: ...aFlex I SLX 100 Oil repellent sealer by Prosoco J Ameripolish Decorative Dyes by American Decorative Concrete K Prosoco LS Guard Lavina SPS Floor Glow by Prosoco PART 3 EXECUTION 3 01 EXAMINATION A Ve...

Page 7: ...Calibra Ceramic bonded diamond until a uniform scratch pattern is achieved Vacuum the floor thoroughly using squeegee vacuum attachment 4 Continue the process with 100 grit Calibra Ceramic bonded diam...

Page 8: ...mage dust and spatter related to the work of this section 1 Repair damage caused by the work of this section 2 Clean dust and spatter from adjoining surfaces C Advise all contractors vendors and other...

Reviews: