Premier VS Infrared Heating System
Page 44
June 04, 2014
INSTALLATION -
Part 2
A
- Vacuum Pump Mounting
1.
Install Vacuum Pump as per designed system mounting location and position.
2.
Ensure that mounting supports are sufficient to withstand the weight and vibration of the Vacuum Pump and
Ventilation System. Welded link chain with a working load limit of at least 200 lbs. (91 kg) is recommended
for mounting vacuum pumps only.
3.
Install using the Vacuum Pump Mounting Kit if purchased. (Chain & threaded rods for ceiling mounting
are NOT included in package.)
4.
Ensure elevation of Inlet will allow for the alignment of the Tubing with a downward slope of ¼” per 10 ft
(7 mm per 3 m) towards the Vacuum Pump.
5.
Ensure that the isolators are placed between the Pump housing and the mounting supports to reduce
vibration transfer to the structure.
See Figure 30, Figure 31 or Figure 32 respectively for mounting type details.
Figure 30: Column Mounting – Recommended Pump Suspension
Mount bracket to
column with
suitable fasteners.
VH010
Mounting Kit
Isolators