COMMISSIONING
Before initial operation verify correct installation of your new
Superwind
using the below
check list.
DONE
5
Verification Chart
Table No. 8.1
Look
also
Section:
Mast
Assembled and erected in accordance with the respective manuals.
Bolts, joints, anchors and braces checked. Mast vertically adjusted.
Grounding / lightning protection:
Mast / support grounded
6.4
Ground wire connected to the grounding bus
6.4
Electrical system:
Batteries correctly installed and electrolyte level o.k.
6.3.4
Charge regulator has been set correctly and connected
6.3.4.2
Power resistor has been set correctly and connected. Installation point
provides adequate heat dissipation
6.3.4.3
Fuse holders has been set and connected
fuses 40 A (12 V system) or 20 A (24 V system) prepared
6.3.5
Stop switch (optional) correctly installed and connected
6.3.6
Ammeter (optional) correctly installed and connected
Cabling in accordance to wiring diagram and correctly connected
6.2.1.1
Correct polarity of all cables and connections
6.3.3
Wind Generator:
Cables connected with correct polarity
6.3.3
Strain relief for cables provided (if necessary)
6.3.2.2
Yaw shaft correctly inserted and set with screws
7.2.1.1
Wind vane correctly tightened with mounting plate, screws tightened
7.3
Rotor blades correctly tightened
7.4.1
Rotor blade screws tightened at 4.5 Nm (3.3 ft. lbs.)
7.4.1
Hub mounted on the generator shaft and tightened at 18 Nm (13.3 ft.
lbs.)
7.4.2
After the installation has been completed correctly and everything has been checked,
disconnect the generator lines from each other and connect them with correct polarity to
the battery. Insert the fuses and if you have a stop switch turn it into RUN-position.
Now your new
Superwind
is ready for operation.
CONGRATULATIONS!
Summary of Contents for 350 12V
Page 1: ...www superwind com Superwind 350 12V 24V Manual North Central and South America regions 01 2017...
Page 2: ...V 01 2017 www superwind com 1 Page intentionally left blank...
Page 52: ...V 01 2017 www superwind com 51 ATTACHMENT A Stop Switch Mounting Guidelines...
Page 53: ...V 01 2017 www superwind com 52 STOP SWITCH Mounting Guidelines Manual 01 2017...
Page 60: ...V 01 2017 www superwind com 59 ATTACHMENT B Superwind Charge Regulator 12V Marine...
Page 61: ...V 01 2017 www superwind com 60 Charge Regulator 12V Marine Instructions Manual 01 2017...
Page 70: ...V 01 2017 www superwind com 69 ATTACHMENT C Superwind Charge Regulator 24V Marine...
Page 71: ...V 01 2017 www superwind com 70 Charge Regulator 24V Marine Instructions Manual...