LOCKZONE 

Wall a

Installation – Commissioning – Maintenance

20160330

Installation

See Figure 1.
1. Cut an opening in the wall according to the wall ope-

ning dimensions specified.

2. Place the commissioning box in the opening.
3. Insert the mounting frame into the commissioning box 

and secure it with screws in the short sides to the com-
missioning box and to the wall structure.

4. The assembly and dismantling of the component parts 

are shown in Figure 1.

5. Press the diffuser face to engage it in the mounting 

frame.

Commissioning 

Commissioning should be carried out with the diffuser 
face mounted. Pull the measurement hose and damper 
adjustment cords out of the air diffuser through the per-
foration. Connect a manometer to the measuring tube. 
The desired commissioning pressure can be calculated 

Figure 1. Installation. Commissioning.

To secure baffle (4) in bayonet catch and to secure the octagonal 
perforated face plate (3) against the duct connection.
1. Commissioning box
2. Damper action, bayonet catch
3. Octagonal air distribution plate
4. Air distribution plate
5. Mounting frame + air diffuser

using the rated coefficient of performance of the air dif-
fuser. Set the damper to the correct blade position, tie a 
commissioning knot in the damper cords to indicate the 
damper position. Then lock the cords against the locking 
screw in the air distribution baffle.
The rated coefficient of performance (K-factor) is specified 
on the identification label of the product and in the rele-
vant commissioning instructions at www.swegon.com. 
See Figure 1.

Maintenance

The air diffuser can be cleaned, if necessary, using luke-
warm water with dishwashing detergent added or by 
vacuum cleaning using a brush nozzle. The duct system 
can be accessed after the air diffuser section has been 
removed, the acoustic baffle has been withdrawn, the air 
distribution discs have been moved to the side and the 
damper has been turned and withdrawn from its holder 
from the inlet. See Figure 1.

q

 = flow reading l/s

p

 = current pressure reading (Pa)

k

 = commissioning factor

k-factor

p

q

k

p

q

=

k

p

q

=

(    )

2

LOCKZONE W

Tomelilla

Sweden

400-200

+ALV 400-200-160-B

K = 15/14,3

k

5