background image

Accessories

Commissioning box:

ALS. The ALS commissioning box is made of galvanized sheet steel 
and contains a removable commissioning damper, fixed measurement 
tapping and sound absorbing material*

)

 with reinforced surface layer.

The ALS commissioning box is available with one or two differences in 
dimension between the inlet and the outlet and also a version for low 
installation where a low overall height is required. The ALS commission-
ing box is then supplied without outlet branch.

*

)

Fire resistance rated to B-s1,d0 in accordance with EN ISO 11925-2.

Installation

Cut the opening in the false ceiling according to the dimension print 
and the table with measurements. Place a mounting frame on top of 
the false ceiling and unfold it to form a square frame around the open-
ing. Secure the frame with screws from the underside. Tighten the 
screws through the false ceiling slab, into the perforation on the long 
sides of the frame. If a flexible tube is used as the connecting duct, 
connect it at this phase of the work, and fasten it to the air diffuser 
with a hose clamp.  Place the diffuser backing box in the opening with 
four angle brackets firmly against the false ceiling. Tighten the screws 
through the angle brackets and into the false ceiling slab and into the 
perforation of the mounting frame. Fasten the diffuser face in the 
safety chain and press it into its spring mounts.

If an ALS commissioning box is used, the sleeve coupling between the 
ALS and the air diffuser can be lengthened using an ordinary circular 
duct of up to 500 mm without having to lengthen the measuring 
tubes and damper adjustment cords. See Figure 1.

Commissioning

Commissioning should be carried out with the diffuser face mounted. 
Pull out the measuring tubes and damper adjustment cords through 
the diffuser face perforations. Connect a manometer to the measuring 
tube. The desired commissioning pressure can be computed by apply-
ing the rated coefficient of performance of the air diffuser. Set the 
damper to the correct blade position, tie a commissioning knot in the 
damper cords to indicate the damper position.

Measurement accuracy and requirement on straight duct before the 
commisioning box, see Figure 1. The requirements of straigh duct 
depends on the type of disturbance before the commissioning box. 
Figure 1 shows a bend, a dimensional change and a T-piece. Other 
types of disturbances requires at least 2xD straight (D = connection 
dimension) for measurement accuracy of ± 10% of the flow.

The K-factor (COP) is specified on the product’s identification label. 
K-factors can also be found in the relevant commissioning instructions 
at www.swegon.com.

Maintenance

The air diffuser can be cleaned, if necessary, using lukewarm water 
with dishwashing detergent added. The duct system can be reached 
by dismantling the diffuser face. Pull the distributor plate in the ALS 
commissioning box aside and then twist the damper unit from of its 
mounting. See Figure 1.

Figure 1. Installation. Commissioning.

0xD / ±5%

0xD / ±5%

2xD / ±10%

LPA

a

Installation – Commissioning – Maintenance

20150101

Reviews: