D400-06-00                                                                                              3                                                                                              I56-286-05R

Installation

WARNING

Remove power from initiating-device circuits before install-
ing detectors.

1. Wire detector per installation guidelines.
2. Line  up  arrows  on  the  detector  with  arrows  on  the 

mounting bracket.

3. Turn the detector clockwise until the detector clicks into 

place.

4. After  all  detectors  have  been  installed,  apply  power  to 

the control unit.

5. Test the detector as described under TESTING.
6. Reset the detector at the System Control Panel.
7. Notify the proper authorities the system is in operation.

CAUTION

Dust covers provide limited protection against airborne dust 
particles  during  shipping.  Dust  covers  MUST  be  removed  
before the smoke detectors can sense smoke. Remove sen-
sors before beginning heavy remodeling or  construction.

CAUTION

Smoke  detectors  are  not  to  be  used  with  detector  guards 
unless  the  combination  has  been  evaluated  and  found 
suitable for that purpose.

Testing

Before testing, notify the proper authorities that the smoke 
detector system is undergoing maintenance, and therefore 
the  system  will  temporarily  be  out  of  service.  Disable 
the  zone  or  system  undergoing  maintenance  to  prevent 
unwanted alarms.

Before  testing  the  detector,  look  for  the  presence  of  the 
flashing LED. If it does not flash, power has been lost to 
the  detector  (check  the  wiring),  or  it  is  defective  (return 
for repair).

���

�������� ����

������

���� �������� ������ ����

� ��� ���� �������� ����

���� ������

������

Figure 4. Top and side views showing position of recessed test  switch:

S0167-00

Detectors  must  be  tested  after  installation  and  following 
periodic  maintenance.  The  2412  and  2424  may  be  tested 
as follows:
A. Recessed Test Switch
    1. A test switch is located on the detector housing (see 

Figure 4).

    2. Push and hold the recessed test switch with a 0.1 inch 

maximum diameter tool.

    3. The detector’s LED should light within 5 seconds.
B. Calibrated Test Card (Model R59-18-00)
    1. Remove the detector cover by placing a small-bladed 

screwdriver  in  the  side  slot  of  the  detector  cover, 
twisting slightly until the cover can be turned coun-
terclockwise for removal.

    2. Insert the NO ALARM end of the test card fully into 

the test slot (see Figure 5), then slide it counterclock-
wise until it stops.

    3. The detector should not alarm after 20 seconds.
    4. Remove  the  test  card  by  sliding  it  clockwise  before 

removing, then insert the ALARM end.

    5. The LED should latch on within 20 seconds, indicat-

ing alarm and annunciating the panel.

    6. Put  the  cover  back  by  gently  rotating  it  clockwise 

until it locks in place.

C. Test Module (System Sensor Model No. MOD400R)
    The MOD400R is used with an analog or digital voltme-

ter to check the detector sensitivity as described in the 
MOD400R  manual.

D. Aerosol Generator (Gemini 501)
    Set the generator to represent 4%/Ft. to 5%/Ft. obscu-

ration  as  described  in  the  Gemini  501  manual.  Using 
the  bowl  shaped  applicator,  apply  aerosol  until  unit 
alarms. Detectors that fail these tests should be cleaned 
as described under MAINTENANCE and retested. If the 
detectors still fail these tests, they should be returned for 
repair.