4-3
4.2.3
The order to pack
Please pack according the following procedure:
1. Place the base plate 1 under the machine and
have both the plate and the machine fastened
with bolts.
2. Install the side plate 2.
3. Install the side plate 3.
4. Install the side plate 4.
5. Install the side plate 5.
6. Install the top plate 6 and pack it.
4.3 Installation of the machine
4.3.1 Have the machine set onto the fastening bolts of the crate base
(1) Tools
Sling, lifting equipment, spanner, movement plate, insertion blocks and level
adjusting blocks.
(2) Procedure
a. After dismantling the wooden crate, get the manuals and tool box out.
b. Remove the fastening bolts.
c. Hook it using sling, lift it up and move to site for installation.
d. Align the ground bolts and the base bores and set the later onto them.
Meanwhile, have the level adjusting blocks inserted to the underneath of the
level adjusting bolts.
e. Remove the lifting equipment and slings.
f. Have nuts for the ground bolts mounted.
Summary of Contents for TPR1230
Page 11: ...1 6 z Gearbox For TPR 1230 TPR 1230H For TPR 1600H TPR 2000H z Hydraulic oil pump...
Page 74: ...9 4 9 4 Electrical circuit diagram For TPR 2000H CE Standard...
Page 83: ...9 13 9 9 Electrical circuit diagram For TPR 1230 Standard...
Page 84: ...9 14 9 10 Electrical circuit diagram For TPR 1230H Standard...
Page 85: ...9 15 9 11 Electrical circuit diagram For TPR 1600H TPR 2000H Standard...