Items that must be followed carefully
206
Chapter 10
QS07
1.
Items that must be followed carefully
The spots as shown below are attached with cards that generate high voltage. Other
personnel than the service man approved by TAJIMA should not open the covers. You
could get an electric shock of high voltage.
Daily maintenance (cleaning, lubrication, greasing, inspection) should be performed by
personnel who has been trained properly.
"Repair" and "Replacement of electrical component" must be done only by the service
personnel assigned and trained by Tajima or qualified technician. (Consult your
distributor.)
When starting operation again, attach all the detached covers as they originally were.
Perform daily maintenance (cleaning, lubrication, greasing, inspection). Neglect of daily
maintenance could cause troubles. Damage due to neglect of daily maintenance may be
judged as "Outside the scope of warranty".
If the machine is not used for a long period, turn the power switch ON in regular intervals.
Although each card of the machine has a backup battery, data may be lost for about one
month because voltage of the battery will come down gradually due to discharge when
power switch is turned off.
Assure enough illumination. Assure 300 lux or more for working areas including
underneath part of the machine table when changing under threads or performing daily
maintenance.
Do not turn ON the power with the main shaft fixed. The machine could be broken.
!
DANGER
!
WARNING
!
CAUTION
Summary of Contents for TEMX-C Series
Page 13: ...To search from the menu key ...
Page 25: ...Inspection before starting work 12 Chapter 1 ...
Page 39: ...How to use each part 26 Chapter 2 ...
Page 40: ... E 1 2 3 4 5 6 7 8 9 10 11 27 PT10 Chapter 3 Screen 1 Screen display 28 2 Message display 31 ...
Page 147: ...Other functions that must be remembered 134 Chapter 5 ...
Page 171: ...To move the frame to the position registered 158 Chapter 6 ...