3-10
OPERATION
OPERATING THE MACHINE
INSPECTION AFTER WARM-UP
After warming up the engine and machine
(hydraulic oil), perform the checks and
inspections described below, and repair if
necessary.
1. Check that the warning lamps and meters
are as follows:
· Are all warning lamps off?
· Is the water temperature level within the
green range?
2. Check that there are no irregularities in the
exhaust color, sound and vibrations.
3. Raise the safety lock lever to the locked
position, and then check that the
operating and travel levers are locked.
Summary of Contents for TB1160W
Page 1: ......
Page 11: ...1 1 SAFETY...
Page 50: ...1 40 SAFETY SAFETY SIGNS DECALS...
Page 51: ...1 41 SAFETY SAFETY SIGNS DECALS...
Page 52: ...1 42 SAFETY SAFETY SIGNS DECALS...
Page 53: ...2 1 CONTROLS...
Page 127: ...3 1 OPERATION...
Page 133: ...3 7 MEMO...
Page 158: ...3 32...
Page 159: ...4 1 TRANSPORT...
Page 163: ...4 5 TRANSPORT Hoisting posture HOISTING THE MACHINE...
Page 166: ...4 8...
Page 167: ...5 1 MAINTENANCE...
Page 246: ...5 80...
Page 247: ...6 1 TROUBLESHOOTING...
Page 249: ...6 3 MEMO...
Page 257: ...6 11 MEMO...
Page 273: ...7 1 SPECIFICATIONS...
Page 275: ...7 3 MEMO...
Page 276: ...7 4 SPECIFICATIONS MACHINE DIMENSIONS MACHINE DIMENSIONS...
Page 278: ...7 6 SPECIFICATIONS OPERATING RANGES 2 Piece boom OPERATING RANGES...
Page 280: ...7 8 MEMO...
Page 282: ...7 10 SPECIFICATIONS 2 Piece boom 2570 mm 101 2 in arm LIFTING CAPACITIES...
Page 283: ...7 11 SPECIFICATIONS 2 Piece boom 2570 mm 101 2 in arm LIFTING CAPACITIES...
Page 284: ...7 12...
Page 285: ...8 1 OPTIONS...
Page 291: ...8 7 MEMO...