5-30
MAINTENANCE
INSPECTING AND ADJUSTING THE
V-BELT
Stop the engine and allow the machine to
cool down before performing
maintenance.
• The engine, muffler, radiator, hydraulic
lines, sliding parts and many other parts
of the machine are hot immediately after
the engine is stopped. Touching these
parts will cause burns.
• Before performing maintenance on the
top of the machine, clean the place you
will work on and observe the following
to prevent falling.
· Do not spill oil or grease.
· Do not leave tools scattered around.
· Watch your step when walking.
• Never jump down from the machine.
Use the steps and handrails when
climbing up and down the machine, and
always support your body at three
points with your hands and feet.
IMPORTANT: The loose belts could result
in bad battery charge, overheat of engine
or early wear of belt. Too tight belts could
damage the water pump or bearing and
belt used to drive the alternator.
IMPORTANT: Do not let any oil or grease
get on the belt.
Inspection
1. Open the engine hood and the
maintenance cover.
2. Press the midpoint of the V-belt between
the pulley (2) and alternator pulley (3) to
check the tension. (approx. 98 N or 22
lbs.).
The slack (A) should be 6.6 to 7.4 mm
(0.26 to 0.29 in).
3. Inspect the V-belt (4) and replace if it is as
follows.
· There are cuts or cracks.
· The belt is worn and touches the bottom
of the V groove in the pulley.
· The belt stretched too loose to be
adjusted.
AFTER THE INITIAL 50 HOURS (ONLY FOR NEW MACHINES)
Summary of Contents for TB1160W
Page 1: ......
Page 11: ...1 1 SAFETY...
Page 50: ...1 40 SAFETY SAFETY SIGNS DECALS...
Page 51: ...1 41 SAFETY SAFETY SIGNS DECALS...
Page 52: ...1 42 SAFETY SAFETY SIGNS DECALS...
Page 53: ...2 1 CONTROLS...
Page 127: ...3 1 OPERATION...
Page 133: ...3 7 MEMO...
Page 158: ...3 32...
Page 159: ...4 1 TRANSPORT...
Page 163: ...4 5 TRANSPORT Hoisting posture HOISTING THE MACHINE...
Page 166: ...4 8...
Page 167: ...5 1 MAINTENANCE...
Page 246: ...5 80...
Page 247: ...6 1 TROUBLESHOOTING...
Page 249: ...6 3 MEMO...
Page 257: ...6 11 MEMO...
Page 273: ...7 1 SPECIFICATIONS...
Page 275: ...7 3 MEMO...
Page 276: ...7 4 SPECIFICATIONS MACHINE DIMENSIONS MACHINE DIMENSIONS...
Page 278: ...7 6 SPECIFICATIONS OPERATING RANGES 2 Piece boom OPERATING RANGES...
Page 280: ...7 8 MEMO...
Page 282: ...7 10 SPECIFICATIONS 2 Piece boom 2570 mm 101 2 in arm LIFTING CAPACITIES...
Page 283: ...7 11 SPECIFICATIONS 2 Piece boom 2570 mm 101 2 in arm LIFTING CAPACITIES...
Page 284: ...7 12...
Page 285: ...8 1 OPTIONS...
Page 291: ...8 7 MEMO...