RAYTHON User Manual V1.0
5.0 Operation
5.1 Double Checking
➢
The system is installed correctly and steady.
➢
Make sure the ground wire is properly connected firmly and reliably.
➢
Make sure the cables are properly connected firmly and reliably.
➢
The DC breaker AC breaker and PV switch is OFF before switching on the inverter
➢
Inspect the Ac input and AC output are correct, and make sure the unit is not short cut.
➢
Make sure the AC input voltage is within the nominal range.
➢
Make sure the PV input voltage is within the nominal range
5.2 Switching on the Battery
➢
Make sure the battery voltage is within the permissible range before turning ON the breaker.
➢
Switch on all batteries
;
Press the On/Off button for 0.5 second to turn on the batteries
➢
Switch on battery switch
5.3 Switch on the Inverter
Please follow the below instructions step by step.
➢
Step 1: Press the On/Off button for 2 seconds to turn on the inverter into the standby mode, the power LED
will light up and the LCD will enter the self diagnostic mode.
➢
Step 2: Wait in the standby mode for 30 seconds, then press the On/Off button again for 1 second to turn on the
inverter into the inverting mode and observe the LCD and the invert LED to make sure the inverter is running
normally.