• Verify that only captive centerpin 75 Ohm Type-F connectors are used on the solid
copper center conductor CATV 75 Ohm cable.
• Verify that the CATV cable is labeled with:
• Fusion Wideband Main Hub port number being used
• RAU identifier
• Carrier (for multiple operator systems)
To connect the CATV cable:
1.
Connect the CATV cables to the F female port on the RAU according to the label
on the cable.
Power is supplied by the Fusion Wideband Main Hub over the CATV cable con-
ductors. Upon power up, the LEDs will blink for two seconds as a visual check
that they are functioning. After the two-second test:
• The
LINK
LED should be green indicating it is receiving power and communi-
cations from the Fusion Wideband Main Hub.
• The
ALARM
LED should be red until the Fusion Wideband Main Hub issues the
band command, within about 20 seconds, then it should be green.
2.
Record which cable you are connecting to the RAU (from the label on the cable).
This information is required for the As-Built Document.
3.
Tie-off cables or use the optional cable manager to avoid damaging the connectors
because of cable strain.
7.4.3.1
Troubleshooting Using RAU LEDs During Installation
• The
LINK
LED should be green and remain green for longer than 90 seconds. The