16
3. Pull the battery tray out using the plastic tabs and then remove
the battery tray.
Figure 3-10: Removing the Battery Tray
4. Install the PDU’s ears to the UPS
Figure 3-11. Install the PDU’s ears to the UPS
5. Select the proper holes in the rail for positioning the cabinet in
the desired location in the rack. Locate the rails at the bottom of
the 3U(3U/6K,5U/10K) space allocated for the each UPS and
EBM.
6. Install the sliding rails in the rack, then install the UPS in the
sliding rail.
17
Figure 3-12. Install the sliding rails
7. For 10K---Install the battery pack and battery protection plate,
then fix the front panel.
Figure 3-13. Installing the Cabinet
8. For 6K---Install the battery tray, and connect the internal battery
connector, then fix the protection plate and the front panel.
9. If installing additional UPSs, repeat from Step 1 to Step 8 for
each cabinet.
3.5.2 Installing the EBMs
Note:
A little of arcing may occur when connecting an EBM to the
UPS. That is normal and not harmed. Plug the EBM cable into the
UPS battery connector quickly and firmly.